2329 S ALSACE AVE 90016
Certificate Information: 2329 S ALSACE AVE 90016
- Application / Permit
- 22014-10000-00435
- Plan Check / Job No.
- B22LA01718
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REAR ADDITION (115sf) TO (E) SFD TO CREATE BED ROOM. REPAIR AND EXTEND FRONT PORCH AND INSTALL OVER ROOF COVER
- Permit Issued
- Issued on 9/15/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | KHUONG TRUONG |
| Corrections Issued | 2/13/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| Plan Check Approved | 8/2/2022 | RICARDO RAMIREZ |
| Issued | 9/15/2022 | APPLICANT |
| CofO in Progress | 7/29/2024 | JUSTIN HAWLEY |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/23/2022 | AMAAN MALIK |
| Address approval | Cleared | 6/27/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | AMAAN MALIK |
Contact Information
| Contractor | Grayson'S Construction Company; Lic. No.: 1042843-B | 4455 ELM AVE LONG BEACH, CA 90807 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/16/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 9/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/30/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/27/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Rough | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/4/2022 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 11/4/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 11/4/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 11/4/2022 | Partial Approval | STUART CHAPMAN |
| MERV13>=Rough | 11/4/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/30/2022 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Approved | BRENDAN MORELLI |
| Wood Frame | 11/30/2022 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 12/19/2022 | Approved | CALEB MEISTER |
| Insulation | 12/19/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 12/28/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 7/16/2024 | Approved | JUSTIN HAWLEY |
| Final | 7/16/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Rough | 7/16/2024 | Approved | JUSTIN HAWLEY |
| MERV13>=Final | 7/16/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 7/16/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 7/24/2024 | SGSOV Not Ready | JUSTIN HAWLEY |
| ELECTRICAL-Final | 7/29/2024 | Approved | JUSTIN HAWLEY |
| Final | 7/29/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 7/29/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 7/29/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | JUSTIN HAWLEY |