2329 S ALSACE AVE 90016

Certificate Information: 2329 S ALSACE AVE 90016

Application / Permit
22014-10000-00435
Plan Check / Job No.
B22LA01718
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION (115sf) TO (E) SFD TO CREATE BED ROOM. REPAIR AND EXTEND FRONT PORCH AND INSTALL OVER ROOF COVER
Permit Issued
Issued on 9/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 2/11/2022 KHUONG TRUONG
Corrections Issued 2/13/2022 KHUONG TRUONG
Building Plans Picked Up 2/16/2022 APPLICANT
Plan Check Approved 8/2/2022 RICARDO RAMIREZ
Issued 9/15/2022 APPLICANT
CofO in Progress 7/29/2024 JUSTIN HAWLEY
CofO Issued 8/5/2024 DEROLD HAUFF
Permit Finaled 8/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/23/2022 AMAAN MALIK
Address approval Cleared 6/27/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/2/2022 AMAAN MALIK

Contact Information

Contractor Grayson'S Construction Company; Lic. No.: 1042843-B 4455 ELM AVE      LONG BEACH, CA 90807
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 9/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/30/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/27/2022 Partial Approval STUART CHAPMAN
Green Building Rough 10/27/2022 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 10/27/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 11/4/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 11/4/2022 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 11/4/2022 Not Ready for Inspection STUART CHAPMAN
Insulation 11/4/2022 Partial Approval STUART CHAPMAN
MERV13>=Rough 11/4/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 11/30/2022 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Approved BRENDAN MORELLI
Wood Frame 11/30/2022 Approved BRENDAN MORELLI
Drywall Nailing 12/19/2022 Approved CALEB MEISTER
Insulation 12/19/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 12/28/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 7/16/2024 Approved JUSTIN HAWLEY
Final 7/16/2024 Corrections Issued JUSTIN HAWLEY
Green Building Rough 7/16/2024 Approved JUSTIN HAWLEY
MERV13>=Final 7/16/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 7/16/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Not Ready JUSTIN HAWLEY
ELECTRICAL-Final 7/29/2024 Approved JUSTIN HAWLEY
Final 7/29/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 7/29/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 7/29/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved JUSTIN HAWLEY