1571 W FAIR PARK AVE 90041
Certificate Information: 1571 W FAIR PARK AVE 90041
- Application / Permit
- 22014-10000-00426
- Plan Check / Job No.
- B22LA01695
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL WITH GROUND AND 2ND FLOOR ADDITION TO An (E) 1-STORY SFD
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | KHEDER ALRAZAA |
| Corrections Issued | 3/7/2022 | KHEDER ALRAZAA |
| Quality Review Completed | 3/18/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 3/24/2022 | APPLICANT |
| Applicant returned to address corrections | 2/8/2023 | KHEDER ALRAZAA |
| Plan Check Approved | 2/16/2023 | KHEDER ALRAZAA |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 8/27/2025 | DAVID WILLIAMS |
| Permit Finaled | 8/29/2025 | DEROLD HAUFF |
| CofO Issued | 8/29/2025 | DEROLD HAUFF |
| Permit Finaled | 8/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/3/2022 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 10/11/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 12/15/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/11/2023 | JEANIE LAM |
Contact Information
| Contractor | Mint Leaf Construction Inc The; Lic. No.: 994908-B | 3756 W AVE 40 SUITE K 497 LOS ANGELES, CA 90065 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/11/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/8/2023 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 8/8/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/1/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/14/2023 | Approved | ROY SPAULDING |
| Wood Frame | 9/14/2023 | Approved | ROY SPAULDING |
| Deputy Wood Construction | 12/13/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/14/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 12/14/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 12/14/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deck | 2/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/29/2024 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 2/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 2/29/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/29/2024 | Approved | CRAIG VAUGHAN |
| Wood Frame | 2/29/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/20/2024 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 3/20/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 3/20/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/20/2024 | Approved | CRAIG VAUGHAN |
| Wood Frame | 3/20/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 3/29/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/29/2024 | Partial Approval | CRAIG VAUGHAN |
| Pre-Inspection | 3/29/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 4/10/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 4/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 6/26/2024 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Final | 12/17/2024 | Corrections Issued | BRENDAN MORELLI |
| Final | 12/17/2024 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 12/17/2024 | Conditional Approval | BRENDAN MORELLI |
| HVAC-Final | 12/17/2024 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/17/2024 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 12/17/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 5/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 5/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/15/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/16/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 7/16/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 8/12/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 8/12/2025 | Approved | DAVID WILLIAMS |
| Final | 8/26/2025 | OK to Issue CofO | DAVID WILLIAMS |