2537 N PANORAMA TER 90039

Certificate Information: 2537 N PANORAMA TER 90039

Application / Permit
22014-10000-00422
Plan Check / Job No.
B22LA01674
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF (E) 2-STORY SINGLE FAMILY DWELLING & ENCLOSE FRONT PORCH
Permit Issued
Issued on 4/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 PRANITA SHAH
Corrections Issued 2/25/2022 PRANITA SHAH
Quality Review Completed 3/2/2022 KEN GILL
Building Plans Picked Up 3/22/2022 APPLICANT
Applicant returned to address corrections 8/16/2022 PRANITA SHAH
Applicant returned to address corrections 2/10/2023 PRANITA SHAH
Plan Check Approved 2/22/2023 PRANITA SHAH
Issued 4/13/2023 APPLICANT
CofO in Progress 11/13/2024 ENRIQUE MIRELES
Permit Finaled 11/19/2024 DEROLD HAUFF
CofO Issued 11/19/2024 DEROLD HAUFF
Permit Finaled 11/19/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/28/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/29/2022 WALLIE JONG
Grading Pre-Inspection Cleared 2/10/2023 PRANITA SHAH

Contact Information

Architect , Mojdehi, Mariam; Lic. No.: C37992       ,
Contractor Eho Consulting Inc; Lic. No.: 1092421-B 1253 DANIELS DR      LOS ANGELES, CA 90035
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/5/2023 Partial Inspection STUART CHAPMAN
Footing/Foundation/Slab 5/30/2023 Corrections Issued JOSEPH MCGARRY
Deputy Drilled-In Anchors 6/12/2023 Partial Approval JEFFREY MEAD
Deputy Steel/Welding 6/12/2023 Partial Approval JEFFREY MEAD
PLUMBING-Rough 7/10/2023 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 7/13/2023 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 8/4/2023 Partial Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 8/4/2023 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 8/17/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/24/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 10/11/2023 Partial Inspection JOSEPH MCGARRY
HVAC-Rough 10/11/2023 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/11/2023 Approved JOSEPH MCGARRY
Deputy Wood Construction 10/13/2023 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 10/16/2023 Partial Approval JOSEPH MCGARRY
Green Building Rough 10/16/2023 Approved JOSEPH MCGARRY
Insulation 10/16/2023 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 11/9/2023 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 11/21/2023 Conditional Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 11/27/2023 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 12/1/2023 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 12/1/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 12/5/2023 Partial Approval JOSEPH MCGARRY
Shower Pan 12/5/2023 Approved JOSEPH MCGARRY
Drywall Nailing 12/8/2023 Approved ALIZAH MAYAGOITIA
Grading Pre-Inspection 12/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 3/29/2024 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 4/2/2024 Approved ENRIQUE MIRELES
Deck 4/19/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Final 7/1/2024 Approved ENRIQUE MIRELES
Final 7/1/2024 Corrections Issued ENRIQUE MIRELES
HVAC-Final 7/1/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/10/2024 Approved ENRIQUE MIRELES
Final 10/10/2024 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 10/10/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 10/10/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Final 11/4/2024 Approved ENRIQUE MIRELES
Final 11/4/2024 OK to Issue CofO ENRIQUE MIRELES