5519 W GEER AVE 90016

Certificate Information: 5519 W GEER AVE 90016

Application / Permit
22014-10000-00411
Plan Check / Job No.
B22LA01580
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION ATTACHED TO EXISTING UNIT PERMIT #18643 MASTER BEDROOM / BATH TOTAL SQ FT 1701
Permit Issued
Issued on 9/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2022 APPLICANT
Assigned to Plan Check Engineer 2/7/2022 SINA KHOSRAVI
Corrections Issued 3/14/2022 ZAW HAN
Building Plans Picked Up 3/29/2022 APPLICANT
Plan Check Approved 9/6/2022 JAD BASMA
Issued 9/6/2022 APPLICANT
CofO in Progress 7/19/2023 JOSE AVILA
Permit Finaled 7/25/2023 DEROLD HAUFF
CofO Issued 7/25/2023 DEROLD HAUFF
Permit Finaled 7/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 2/17/2022 JASON SHEETS
Tenant Habitability Plan Cleared 5/10/2022 ISMAEL HERNANDEZ
Roof/Waste drainage to street Cleared 5/13/2022 ABEL CASILLAS
Sewer availability Cleared 5/13/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 5/20/2022 ABEL CASILLAS
Construction near power lines Cleared 6/21/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/19/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/27/2022 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 11/4/2022 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 11/21/2022 Approved JOSE AVILA
ELECTRICAL-Rough 1/25/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 1/25/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Corrections Issued JOSE AVILA
Wood Frame 2/23/2023 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 3/2/2023 Approved JOSE AVILA
Green Building Rough 3/2/2023 Corrections Issued JOSE AVILA
Rough-Elec/Plmb/HVAC 3/2/2023 Approved JOSE AVILA
Insulation 3/9/2023 Approved JOSE AVILA
Interior/Exterior Lathing 3/9/2023 Approved JOSE AVILA
Drywall Nailing 3/14/2023 Approved JOSE AVILA
Green Building Rough 3/14/2023 Approved JOSE AVILA
Shower Pan 3/20/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 5/19/2023 Corrections Issued JOSE AVILA
PLUMBING-Final 5/24/2023 Approved JOSE AVILA
HVAC-Final 5/26/2023 Conditional Approval JOSE AVILA
ELECTRICAL-Final 5/30/2023 Approved JOSE AVILA
Green Building Final 5/30/2023 Approved JOSE AVILA
HVAC-Final 5/30/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 5/30/2023 Approved JOSE AVILA
Final 7/19/2023 OK to Issue CofO JOSE AVILA