636 N LAUREL AVE 90048
Certificate Information: 636 N LAUREL AVE 90048
- Application / Permit
- 22014-10000-00410
- Plan Check / Job No.
- B22LA01576
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO AN EXISTING SFD. CONVERT PARTION OF EXISITING SFD.
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/8/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/17/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| Applicant returned to address corrections | 10/14/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/26/2022 | MAHNAZ NOURHASHEMI |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 3/17/2026 | JOSH MEISTER |
| Permit Finaled | 3/20/2026 | DEROLD HAUFF |
| CofO Issued | 3/20/2026 | DEROLD HAUFF |
| Permit Finaled | 3/20/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/11/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2022 | TREVOR QUAN |
| Permit | Cleared | 6/21/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 8/18/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/26/2022 | TREVOR QUAN |
| Trees in Parkway | Cleared | 10/7/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Under Construction; Lic. No.: 883832-B | 2671 N BEVERLY GLEN BLVD LOS ANGELES, CA 90077 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/1/2023 | Partial Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 12/26/2023 | Approved | LILIANA PORTILLO |
| METHANE-Barrier | 12/26/2023 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 12/26/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | No Access for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Partial Approval | AMIR NAZARIAN |
| Deputy Wood Construction | 3/21/2024 | Conditional Approval | AMIR NAZARIAN |
| Structural Steel Frame | 4/8/2024 | Corrections Issued | AMIR NAZARIAN |
| Wood Frame | 4/8/2024 | Corrections Issued | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Partial Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 6/25/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 6/25/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| METHANE-Rough | 6/25/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 6/27/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 7/1/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 7/2/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 7/2/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 7/2/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| METHANE-Rough | 7/2/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Structural Steel Frame | 7/2/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Rough | 7/3/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 7/3/2024 | Conditional Approval | AMIR NAZARIAN |
| PLUMBING-Rough | 7/3/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 7/24/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 7/24/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| METHANE-Rough | 7/24/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 7/24/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 9/30/2024 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 10/7/2024 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 10/9/2024 | Approved | JOSE MACIAS |
| Sewer | 2/28/2025 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 3/18/2025 | Conditional Approval | JOSE MACIAS |
| Special/Order Compliance | 3/21/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 7/21/2025 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 7/21/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 7/25/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 7/28/2025 | Approved | JOSE MACIAS |
| HVAC-Final | 7/28/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 8/26/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/28/2026 | Approved | JOSH MEISTER |
| Final | 1/28/2026 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 1/28/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Rough | 1/28/2026 | Approved | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Not Required | JOSH MEISTER |
| Smoke Detectors | 1/28/2026 | Approved | JOSH MEISTER |
| Final | 2/6/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Final | 2/6/2026 | Not Ready for Inspection | JOSH MEISTER |
| Final | 3/13/2026 | OK to Issue CofO | JOSH MEISTER |
| Green Building Final | 3/13/2026 | Approved | JOSH MEISTER |