636 N LAUREL AVE 90048

Certificate Information: 636 N LAUREL AVE 90048

Application / Permit
22014-10000-00410
Plan Check / Job No.
B22LA01576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO AN EXISTING SFD. CONVERT PARTION OF EXISITING SFD.
Permit Issued
Issued on 10/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 MAHNAZ NOURHASHEMI
Corrections Issued 3/8/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 3/17/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/23/2022 APPLICANT
Applicant returned to address corrections 10/14/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 10/26/2022 MAHNAZ NOURHASHEMI
Issued 10/27/2022 APPLICANT
CofO in Progress 3/17/2026 JOSH MEISTER
Permit Finaled 3/20/2026 DEROLD HAUFF
CofO Issued 3/20/2026 DEROLD HAUFF
Permit Finaled 3/20/2026 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 4/11/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/7/2022 TREVOR QUAN
Permit Cleared 6/21/2022 TREVOR QUAN
Low Impact Development Cleared 8/18/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/26/2022 TREVOR QUAN
Trees in Parkway Cleared 10/7/2022 ADALBERTO VERA

Contact Information

Contractor Under Construction; Lic. No.: 883832-B 2671 N BEVERLY GLEN BLVD      LOS ANGELES, CA 90077
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/1/2023 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 12/26/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 12/26/2023 Approved LILIANA PORTILLO
METHANE-Barrier 12/26/2023 Approved LILIANA PORTILLO
METHANE-Subgrade 12/26/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 No Access for Inspection AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Partial Approval AMIR NAZARIAN
Deputy Wood Construction 3/21/2024 Conditional Approval AMIR NAZARIAN
Structural Steel Frame 4/8/2024 Corrections Issued AMIR NAZARIAN
Wood Frame 4/8/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Partial Approval AMIR NAZARIAN
BUILDING-Rough-Frame 6/25/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 6/25/2024 Not Ready for Inspection AMIR NAZARIAN
METHANE-Rough 6/25/2024 Not Ready for Inspection AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Not Ready for Inspection AMIR NAZARIAN
HVAC-Rough 6/27/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 7/1/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 7/2/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 7/2/2024 Approved AMIR NAZARIAN
Green Building Rough 7/2/2024 Not Ready for Inspection AMIR NAZARIAN
METHANE-Rough 7/2/2024 Not Ready for Inspection AMIR NAZARIAN
Structural Steel Frame 7/2/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 7/3/2024 Approved AMIR NAZARIAN
HVAC-Rough 7/3/2024 Conditional Approval AMIR NAZARIAN
PLUMBING-Rough 7/3/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 7/24/2024 Approved AMIR NAZARIAN
Green Building Rough 7/24/2024 Not Ready for Inspection AMIR NAZARIAN
METHANE-Rough 7/24/2024 Approved AMIR NAZARIAN
Wood Frame 7/24/2024 Approved AMIR NAZARIAN
Drywall Nailing 9/30/2024 Corrections Issued JOSE MACIAS
Drywall Nailing 10/7/2024 Corrections Issued JOSE MACIAS
Drywall Nailing 10/9/2024 Approved JOSE MACIAS
Sewer 2/28/2025 Approved JOSE MACIAS
Deputy Wood Construction 3/18/2025 Conditional Approval JOSE MACIAS
Special/Order Compliance 3/21/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Final 7/21/2025 Corrections Issued JOSE MACIAS
HVAC-Final 7/21/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Final 7/25/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Final 7/28/2025 Approved JOSE MACIAS
HVAC-Final 7/28/2025 Approved JOSE MACIAS
PLUMBING-Final 8/26/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/28/2026 Approved JOSH MEISTER
Final 1/28/2026 Corrections Issued JOSH MEISTER
Green Building Final 1/28/2026 Not Ready for Inspection JOSH MEISTER
Green Building Rough 1/28/2026 Approved JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Not Required JOSH MEISTER
Smoke Detectors 1/28/2026 Approved JOSH MEISTER
Final 2/6/2026 Not Ready for Inspection JOSH MEISTER
Green Building Final 2/6/2026 Not Ready for Inspection JOSH MEISTER
Final 3/13/2026 OK to Issue CofO JOSH MEISTER
Green Building Final 3/13/2026 Approved JOSH MEISTER