1810 S BENTLEY AVE 90025
Certificate Information: 1810 S BENTLEY AVE 90025
- Application / Permit
- 22014-10000-00394
- Plan Check / Job No.
- B22LA01522
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan apartment ADU. CONVERTING EXISTING STORAGE TO ONE ACCESSORY DWELLING UNIT per CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Current Status
- Issued on 2/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | MONICA RAMIREZ |
| Corrections Issued | 3/8/2022 | MONICA RAMIREZ |
| Quality Review Completed | 3/11/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/14/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 5/9/2023 | MONICA RAMIREZ |
| Applicant returned to address corrections | 6/8/2023 | MONICA RAMIREZ |
| Plan Check Approved | 2/9/2024 | MONICA RAMIREZ |
| Issued | 2/22/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 6/7/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 3/20/2023 | ROBERT SANCHEZ |
| Fire Marshal Fire Life Safety | Cleared | 5/4/2023 | WILLIAM JOHNS |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | , |
| Contractor | Perluss Sheldon K; Lic. No.: 759817-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 10/11/2024 | Corrections Issued | MICHAEL PETRUSKO |
| Final | 11/26/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Final | 11/26/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Rough | 11/26/2024 | Approved | RICARDO ROBLES |
| MERV13>=Final | 11/26/2024 | Approved | RICARDO ROBLES |
| MERV13>=Rough | 11/26/2024 | Approved | RICARDO ROBLES |
| METHANE-Final | 11/26/2024 | Approved | RICARDO ROBLES |
| METHANE-Rough | 11/26/2024 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 11/26/2024 | Approved | RICARDO ROBLES |