1810 S BENTLEY AVE 90025

Certificate Information: 1810 S BENTLEY AVE 90025

Application / Permit
22014-10000-00394
Plan Check / Job No.
B22LA01522
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan apartment ADU. CONVERTING EXISTING STORAGE TO ONE ACCESSORY DWELLING UNIT per CA Govt. Code 65852.2(e)(1)(C)
Permit Issued
Issued on 2/22/2024
Issuing Office
Current Status
Issued on 2/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 MONICA RAMIREZ
Corrections Issued 3/8/2022 MONICA RAMIREZ
Quality Review Completed 3/11/2022 HERNAN ARREOLA
Applicant returned to address corrections 6/14/2022 MONICA RAMIREZ
Applicant returned to address corrections 5/9/2023 MONICA RAMIREZ
Applicant returned to address corrections 6/8/2023 MONICA RAMIREZ
Plan Check Approved 2/9/2024 MONICA RAMIREZ
Issued 2/22/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/7/2022 CATHERINE ADROVER
Sewer availability Cleared 6/7/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 7/28/2022 CATHERINE ADROVER
Specific Plan Cleared 3/20/2023 ROBERT SANCHEZ
Fire Marshal Fire Life Safety Cleared 5/4/2023 WILLIAM JOHNS

Contact Information

Contractor Cal - Quake Construction Inc; Lic. No.: 759817-B       ,
Contractor Perluss Sheldon K; Lic. No.: 759817-B       ,
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 10/11/2024 Corrections Issued MICHAEL PETRUSKO
Final 11/26/2024 Not Ready for Inspection RICARDO ROBLES
Green Building Final 11/26/2024 Not Ready for Inspection RICARDO ROBLES
Green Building Rough 11/26/2024 Approved RICARDO ROBLES
MERV13>=Final 11/26/2024 Approved RICARDO ROBLES
MERV13>=Rough 11/26/2024 Approved RICARDO ROBLES
METHANE-Final 11/26/2024 Approved RICARDO ROBLES
METHANE-Rough 11/26/2024 Approved RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Approved RICARDO ROBLES
Smoke Detectors 11/26/2024 Approved RICARDO ROBLES