541 W SOLANO AVE UNIT 1,2,3 90012
Certificate Information: 541 W SOLANO AVE UNIT 1,2,3 90012
- Application / Permit
- 22014-10000-00380
- Plan Check / Job No.
- B22LA01486
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) STORAGE(941SF), GARAGE(255SF) AND OFFICE(258SF) TO 3 ADUs AT LOWER LEVEL OF (E) APARTMENT.
- Permit Issued
- Issued on 7/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | FERNANDO FLORES |
| Corrections Issued | 2/5/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 4/23/2022 | FERNANDO FLORES |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Applicant returned to address corrections | 6/30/2022 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/15/2023 | MINA HABILI |
| Plan Check Approved | 7/6/2023 | SAMUEL GONZALEZ |
| Issued | 7/6/2023 | APPLICANT |
| CofO in Progress | 12/23/2025 | RONALD JIMENEZ |
| Permit Finaled | 12/23/2025 | ERNESTO CORRAL |
| CofO Issued | 12/23/2025 | ERNESTO CORRAL |
| Permit Finaled | 12/23/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/16/2022 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 3/29/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 4/4/2022 | AMAAN MALIK |
| Fire Marshal Fire Life Safety | Cleared | 6/28/2022 | PEJMAN NOORI |
| Grading Pre-Inspection | Cleared | 6/30/2022 | FERNANDO FLORES |
| Miscellaneous | Cleared | 6/30/2022 | RICARDO RAMIREZ |
Contact Information
| Contractor | R L G Construction; Lic. No.: 1023091-B | 5730 LA MIRADA AVENUE LOS ANGELES, CA 90038 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/11/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Wall Anchors | 7/28/2023 | Approved | JULIAN CAPUCETTI |
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Approved | JULIAN CAPUCETTI |
| Footing/Foundation/Slab | 8/11/2023 | Approved | JULIAN CAPUCETTI |
| Wood Frame | 8/18/2023 | Partial Approval | JULIAN CAPUCETTI |
| Structural Steel Frame | 8/29/2023 | Approved | ALAN MORELOS |
| Wood Frame | 9/12/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Wood Frame | 9/14/2023 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 9/19/2023 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 9/25/2023 | Approved | JULIAN CAPUCETTI |
| Drywall Nailing | 9/27/2023 | Partial Approval | JULIAN CAPUCETTI |
| Insulation | 9/27/2023 | Partial Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 10/4/2023 | Approved | RAMAZANALI ALMASI |
| Special/Order Compliance | 12/8/2023 | Approved | RAMAZANALI ALMASI |
| Final | 5/28/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 5/28/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 5/28/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 6/6/2024 | Partial Approval | RONALD JIMENEZ |
| Green Building Final | 6/6/2024 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 6/6/2024 | Approved | RONALD JIMENEZ |
| Final | 12/22/2025 | OK to Issue CofO | RONALD JIMENEZ |