4910 S HARVARD BLVD 90062
Certificate Information: 4910 S HARVARD BLVD 90062
- Application / Permit
- 22014-10000-00370
- Plan Check / Job No.
- B22LA01451
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH AN ADDITION TO A DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 7/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2022 | CARLOS MONTES |
| Corrections Issued | 2/1/2022 | CARLOS MONTES |
| Plan Check Approved | 3/12/2022 | CARLOS MONTES |
| Issued | 4/13/2022 | APPLICANT |
| CofO in Progress | 7/13/2023 | SABAS ALONSO |
| Permit Finaled | 7/20/2023 | DEROLD HAUFF |
| CofO Issued | 7/20/2023 | DEROLD HAUFF |
| Permit Finaled | 7/20/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | CINDY QI |
| Sewer availability | Cleared | 3/1/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/27/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/27/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 6/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 6/8/2022 | Approved | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 6/8/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/11/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/11/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 8/11/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/11/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 8/11/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/25/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/25/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/25/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/13/2022 | Approved | SABAS ALONSO |
| Insulation | 9/13/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/13/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 9/26/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/26/2022 | Approved | SABAS ALONSO |
| Shower Pan | 9/26/2022 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 11/21/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/11/2023 | Corrections Issued | SABAS ALONSO |
| Final | 1/11/2023 | Corrections Issued | SABAS ALONSO |
| Gas Test | 1/11/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 1/11/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 1/11/2023 | Approved | SABAS ALONSO |
| Service/Power Release | 1/11/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 3/14/2023 | Approved | SABAS ALONSO |
| Final | 3/14/2023 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 3/14/2023 | Approved | SABAS ALONSO |
| Green Building Final | 3/14/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 3/14/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 3/14/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 3/14/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/1/2023 | Approved | STUART CHAPMAN |
| Final | 6/1/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 6/1/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 6/1/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | STUART CHAPMAN |
| Final | 6/21/2023 | Corrections Issued | SABAS ALONSO |
| Final | 7/12/2023 | OK to Issue CofO | SABAS ALONSO |