4910 S HARVARD BLVD 90062

Certificate Information: 4910 S HARVARD BLVD 90062

Application / Permit
22014-10000-00370
Plan Check / Job No.
B22LA01451
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH AN ADDITION TO A DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofO Issued on 7/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 1/31/2022 CARLOS MONTES
Corrections Issued 2/1/2022 CARLOS MONTES
Plan Check Approved 3/12/2022 CARLOS MONTES
Issued 4/13/2022 APPLICANT
CofO in Progress 7/13/2023 SABAS ALONSO
Permit Finaled 7/20/2023 DEROLD HAUFF
CofO Issued 7/20/2023 DEROLD HAUFF
Permit Finaled 7/20/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/22/2022 CINDY QI
Roof/Waste drainage to street Cleared 2/22/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/1/2022 CINDY QI
Sewer availability Cleared 3/1/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/27/2022 Approved SABAS ALONSO
Underground Mechanical 5/27/2022 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 6/3/2022 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 6/8/2022 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 6/8/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/11/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 8/11/2022 Approved SABAS ALONSO
Green Building Rough 8/11/2022 Approved SABAS ALONSO
HVAC-Rough 8/11/2022 Approved SABAS ALONSO
PLUMBING-Rough 8/11/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 8/25/2022 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/25/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 8/25/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/13/2022 Approved SABAS ALONSO
Insulation 9/13/2022 Approved SABAS ALONSO
PLUMBING-Rough 9/13/2022 Approved SABAS ALONSO
Drywall Nailing 9/26/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 9/26/2022 Approved SABAS ALONSO
Shower Pan 9/26/2022 Corrections Issued SABAS ALONSO
Shower Pan 11/21/2022 Approved SABAS ALONSO
ELECTRICAL-Final 1/11/2023 Corrections Issued SABAS ALONSO
Final 1/11/2023 Corrections Issued SABAS ALONSO
Gas Test 1/11/2023 Approved SABAS ALONSO
HVAC-Final 1/11/2023 Corrections Issued SABAS ALONSO
PLUMBING-Final 1/11/2023 Approved SABAS ALONSO
Service/Power Release 1/11/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 3/14/2023 Approved SABAS ALONSO
Final 3/14/2023 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 3/14/2023 Approved SABAS ALONSO
Green Building Final 3/14/2023 Approved SABAS ALONSO
HVAC-Final 3/14/2023 Approved SABAS ALONSO
PLUMBING-Final 3/14/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 3/14/2023 Approved SABAS ALONSO
ELECTRICAL-Final 6/1/2023 Approved STUART CHAPMAN
Final 6/1/2023 Corrections Issued STUART CHAPMAN
HVAC-Final 6/1/2023 Approved STUART CHAPMAN
PLUMBING-Final 6/1/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved STUART CHAPMAN
Final 6/21/2023 Corrections Issued SABAS ALONSO
Final 7/12/2023 OK to Issue CofO SABAS ALONSO