4035 1/2 S MARCASEL AVE 90066

Certificate Information: 4035 1/2 S MARCASEL AVE 90066

Application / Permit
22014-10000-00367
Plan Check / Job No.
B21LA24523
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING AN EXISTING ACCESSORY BUILDING (ONLY SECOND FLOOR) TO AN ADU PER STATE LAW. (ADU: 877sf)
Permit Issued
Issued on 9/15/2022
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 JOE VO
Corrections Issued 2/4/2022 CARLOS MONTES
Applicant returned to address corrections 4/12/2022 JOE VO
Plan Check Approved 9/13/2022 JOE VO
Issued 9/15/2022 APPLICANT
CofO in Progress 11/8/2024 JESUS PINEDA
CofO Issued 11/13/2024 RICHARD STEINBACH
Permit Finaled 11/13/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/1/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 7/1/2022 SAUL GARCIA
Sewer availability Cleared 7/1/2022 SAUL GARCIA
Specific Plan Cleared 7/27/2022 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/5/2022 Not Ready for Inspection JESUS RODRIGUEZ
Final 10/5/2022 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 10/5/2022 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 10/5/2022 Not Ready for Inspection JESUS RODRIGUEZ
Pre-Inspection 10/6/2022 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/25/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/25/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 7/25/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/25/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 7/25/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 7/25/2023 Corrections Issued JESUS RODRIGUEZ
Deputy Drilled-In Anchors 2/28/2024 Conditional Approval JESUS RODRIGUEZ
Final 10/23/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 10/23/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 10/23/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 11/6/2024 Approved JESUS PINEDA
Final 11/6/2024 OK to Issue CofO JESUS PINEDA
HVAC-Final 11/6/2024 Approved JESUS PINEDA
PLUMBING-Final 11/6/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 11/6/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 11/6/2024 Approved JESUS PINEDA