3829 N LATROBE ST 90031
Certificate Information: 3829 N LATROBE ST 90031
- Application / Permit
- 22014-10000-00364
- Plan Check / Job No.
- B22LA01427
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND ALTERATION TO AN EXISTING SINGLE FAMILY DWELLING. INSTALL AUTOMATIC FIRE SPRINKLERS UNDER SEPARATE PERMIT. 1 OF 3
- Permit Issued
- Issued on 10/26/2022
- Issuing Office
- Metro
- Current Status
- Issued on 10/26/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | ALBERT SERVIN |
| Corrections Issued | 2/14/2022 | ALBERT SERVIN |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| Quality Review Completed | 2/16/2022 | KEN GILL |
| Applicant returned to address corrections | 8/30/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 9/1/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 9/7/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 9/8/2022 | ALBERT SERVIN |
| Plan Check Approved | 10/20/2022 | ALBERT SERVIN |
| Issued | 10/26/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/22/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 2/22/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 2/22/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 2/22/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 2/22/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 3/30/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 4/11/2022 | LAURINDA MEADE |
| "D" conditions | Cleared | 5/4/2022 | LOUIS ORTEGA |
| "Q" conditions | Cleared | 5/4/2022 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 5/4/2022 | LOUIS ORTEGA |
| Private street | Cleared | 5/4/2022 | LOUIS ORTEGA |
| Low Impact Development | Cleared | 7/13/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 9/6/2022 | JEANETTE VONG |
| Building over 36-ft | Cleared | 9/7/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/20/2022 | ALBERT SERVIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 600 WILSHIRE BLVD 760 LOS ANGELES, CA 90017 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/4/2023 | Partial Inspection | AMY COLIN |
| Footing/Foundation/Slab | 5/23/2023 | Partial Approval | AMY COLIN |
| Piling/Pier/Caisson | 5/23/2023 | Approved | AMY COLIN |
| Deputy Reinf. Concrete | 7/21/2023 | Conditional Approval | AMY COLIN |
| Footing/Foundation/Slab | 7/24/2023 | Partial Approval | AMY COLIN |
| Deputy Reinf. Concrete | 7/26/2023 | Conditional Approval | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Not Ready for Inspection | AMY COLIN |
| Deputy Reinf. Concrete | 8/11/2023 | Conditional Approval | AMY COLIN |
| Reinforced Concrete Frame | 8/14/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 9/12/2023 | Partial Approval | AMY COLIN |
| Deputy Drilled-In Anchors | 9/22/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 9/22/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 9/25/2023 | Conditional Approval | AMY COLIN |
| Deputy Drilled-In Anchors | 10/2/2023 | Conditional Approval | AMY COLIN |
| Deputy Reinf. Concrete | 10/2/2023 | Conditional Approval | AMY COLIN |
| Reinforced Concrete Frame | 10/3/2023 | Partial Approval | AMY COLIN |
| Deputy Reinf. Concrete | 10/6/2023 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 10/12/2023 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 10/12/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 10/12/2023 | Partial Approval | AMY COLIN |
| Wood Frame | 10/12/2023 | Not Ready for Inspection | AMY COLIN |
| Deputy Reinf. Concrete | 10/13/2023 | Conditional Approval | AMY COLIN |
| Deputy Reinf. Concrete | 11/1/2023 | Conditional Approval | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 11/1/2023 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 12/26/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Partial Approval | AMY COLIN |
| Green Building Rough | 12/26/2023 | Not Ready for Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 12/26/2023 | Not Ready for Inspection | AMY COLIN |
| Deputy Reinf. Concrete | 1/18/2024 | Approved | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 1/18/2024 | Approved | AMY COLIN |
| Pre-Inspection | 6/11/2024 | Partial Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 9/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 9/25/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 9/25/2024 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 9/25/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 10/2/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/8/2024 | Corrections Issued | LILIANA PORTILLO |
| Special/Order Compliance | 10/8/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/29/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/29/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/29/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/29/2024 | Partial Approval | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 10/29/2024 | Approved | LILIANA PORTILLO |
| Insulation | 11/7/2024 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 11/7/2024 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/3/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 5/19/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 5/19/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 5/19/2026 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 5/19/2026 | Conditional Approval | NICHOLAS LOPEZ |
| PLUMBING-Final | 5/19/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/19/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 5/19/2026 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 6/3/2026 | Approved | OSVALDO PARAMO |
| Final | 6/3/2026 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 6/3/2026 | Approved | OSVALDO PARAMO |