1663 W 215TH ST 90501
Certificate Information: 1663 W 215TH ST 90501
- Application / Permit
- 22014-10000-00351
- Plan Check / Job No.
- B22LA01385
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED LAUNDRY ROOM AND FULL BATHROOM ADDITION AT REAR OF (E) SFD. CONSTRUCTION PER ENGINEER OF RECORD
- Permit Issued
- Issued on 10/19/2022
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/7/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 4/6/2022 | ADAM HEGAZI |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| Issued | 10/19/2022 | APPLICANT |
| CofO in Progress | 11/30/2023 | EUGENE CASSIDY |
| CofO Issued | 12/5/2023 | ANSON MAGLASANG |
| Permit Finaled | 12/5/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/23/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 3/23/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2022 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Villanueva,, Arturo Jularbal; Lic. No.: C38897 | 1746 LAKME AVE WILMINGTON, CA 90744 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2023 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 5/16/2023 | Approved | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 6/1/2023 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/5/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 6/9/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/29/2023 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 7/5/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 7/12/2023 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/27/2023 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 7/27/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/24/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 8/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 8/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/21/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 9/21/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 9/21/2023 | Approved | EUGENE CASSIDY |
| Insulation | 9/21/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/21/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/3/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/3/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 10/3/2023 | Approved | EUGENE CASSIDY |
| Final | 11/8/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 11/8/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 11/8/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/29/2023 | Approved | EUGENE CASSIDY |
| Final | 11/29/2023 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 11/29/2023 | Approved | EUGENE CASSIDY |
| HVAC-Final | 11/29/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 11/29/2023 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 11/29/2023 | Approved | EUGENE CASSIDY |