2300 N COMMONWEALTH AVE 90027
Certificate Information: 2300 N COMMONWEALTH AVE 90027
- Application / Permit
- 22014-10000-00348
- Plan Check / Job No.
- B22LA01353
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RENOVATE/ REMODEL OF RESIDENTIAL BUILDING AND PATIO ADDITION. ADDITION OF BATHROOM ON 1ST FLOOR.
- Permit Issued
- Issued on 2/14/2023
- Issuing Office
- Current Status
- CofO Issued on 3/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | SUNMIN LEE |
| Corrections Issued | 3/3/2022 | SUNMIN LEE |
| Quality Review Completed | 3/11/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Applicant returned to address corrections | 9/7/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 1/19/2023 | SUNMIN LEE |
| Plan Check Approved | 2/7/2023 | SUNMIN LEE |
| Issued | 2/14/2023 | APPLICANT |
| CofO in Progress | 3/21/2024 | ENRIQUE MIRELES |
| CofO Issued | 3/26/2024 | RONALD MYRICK |
| Permit Finaled | 3/26/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 7/8/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/8/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 7/25/2022 | VASIL MIHALEV |
| Low Impact Development | Cleared | 1/24/2023 | CHRIS VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazarians,, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 4/19/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 5/22/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/25/2023 | Conditional Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 5/25/2023 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/30/2023 | Partial Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/30/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/30/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/30/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/15/2023 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 6/15/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 6/15/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 7/28/2023 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 7/28/2023 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 8/7/2023 | Approved | JOSEPH MCGARRY |
| Shower Pan | 8/7/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/23/2023 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 2/29/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 2/29/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/29/2024 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/19/2024 | Approved | ENRIQUE MIRELES |
| Final | 3/19/2024 | OK to Issue CofO | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/19/2024 | Approved | ENRIQUE MIRELES |
| Green Building Final | 3/19/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/19/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/19/2024 | Approved | ENRIQUE MIRELES |