5149 N FULTON AVE 91423
Certificate Information: 5149 N FULTON AVE 91423
- Application / Permit
- 22014-10000-00312
- Plan Check / Job No.
- B22LA01274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CHANGE (E) GARAGE TO ADU 2 STORY ADDITION WITH ROOF DECK. TOTAL AREA 1,116 SF PER DETACHED ADU - LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | ADRIANA LOPEZ |
| Corrections Issued | 3/1/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 3/2/2022 | SAI KHUM |
| Building Plans Picked Up | 3/7/2022 | APPLICANT |
| Plan Check Approved | 6/24/2022 | ADRIANA LOPEZ |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 8/3/2023 | MISAEL ESPARZA |
| CofO in Progress | 8/7/2023 | MISAEL ESPARZA |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
| CofO Issued | 10/23/2023 | RUBEN SALAS |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/9/2022 | JOSE DUARTE-DIAZ |
| Miscellaneous | Cleared | 3/22/2022 | RUBEN VASQUEZ |
| ZI | Cleared | 3/22/2022 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 5/9/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/19/2022 | Partial Approval | CALEB MEISTER |
| Gas Test | 8/23/2022 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 8/23/2022 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/25/2022 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 8/25/2022 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/2/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/2/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/13/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/22/2022 | Conditional Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 11/9/2022 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 12/19/2022 | Conditional Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/22/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/22/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 12/22/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 12/22/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/10/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/10/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 1/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 1/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 1/10/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 1/23/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/30/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 1/30/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/30/2023 | Conditional Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 2/10/2023 | Approved | MISAEL ESPARZA |
| Insulation | 2/15/2023 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/15/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/24/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 2/24/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 3/3/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/3/2023 | Approved | MISAEL ESPARZA |
| Gas Test | 6/2/2023 | No Access for Inspection | JOHN COLEMAN |
| ELECTRICAL-Final | 7/6/2023 | Approved | MISAEL ESPARZA |
| Final | 7/6/2023 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/6/2023 | Approved | MISAEL ESPARZA |
| Green Building Final | 7/6/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 7/6/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 7/6/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 7/6/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 7/11/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 7/11/2023 | Approved | THOMAS FINNILA |
| Final | 7/31/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 7/31/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | MISAEL ESPARZA |
| Final | 8/7/2023 | OK to Issue CofO | MISAEL ESPARZA |