871-873 W 29TH ST 90731

Certificate Information: 871-873 W 29TH ST 90731

Application / Permit
22014-10000-00306
Plan Check / Job No.
B22LA01251
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING STORAGE ROOM AND ADDITION TO ACCESSORY DWELLING UNITS PER STATE LAW
Permit Issued
Issued on 2/14/2024
Issuing Office
Metro
Current Status
Issued on 2/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 VU NGUYEN
Corrections Issued 2/17/2022 VU NGUYEN
Quality Review Completed 2/22/2022 EUGENE BARBEAU
Building Plans Picked Up 2/24/2022 APPLICANT
Plan Check Approved 12/4/2023 VU NGUYEN
Issued 2/14/2024 APPLICANT

Permit Application Clearance Information

Hold Cleared 2/14/2022 JASON SHEETS
Address approval Cleared 4/14/2022 ERIK BEASLEY
Roof/Waste drainage to street Cleared 5/6/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 6/3/2022 ERIK BEASLEY
Sewer availability Cleared 6/3/2022 ERIK BEASLEY
Grading Pre-Inspection Cleared 11/18/2022 KIRK LINKLATER
Miscellaneous Cleared 11/14/2023 MAXFIELD VERMY

Contact Information

Contractor Choe Craig; Lic. No.: 867838-B 3183 WILSHIRE BLVD   196 - E33    LOS ANGELES, CA 90010
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/9/2024 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 8/19/2024 Not Ready for Inspection JOEY BUCHANAN
Deputy Drilled-In Anchors 12/3/2024 Approved JOEY BUCHANAN
Footing/Foundation/Slab 12/16/2024 Corrections Issued MICHAEL PETRUSKO
Pre-Inspection 12/16/2024 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 2/10/2025 Approved JOEY BUCHANAN
Insulation 4/25/2025 Corrections Issued JOEY BUCHANAN
Insulation 4/29/2025 Approved JOEY BUCHANAN
Wood Frame 4/29/2025 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 5/6/2025 Conditional Approval MICHAEL PETRUSKO
Insulation 5/7/2025 Approved MICHAEL PETRUSKO
Wood Frame 5/7/2025 Approved MICHAEL PETRUSKO
Drywall Nailing 5/28/2025 Approved MICHAEL PETRUSKO
Interior/Exterior Lathing 5/28/2025 Approved MICHAEL PETRUSKO
Special/Order Compliance 5/11/2026 No Access for Inspection MICHAEL PETRUSKO