1114 1/2 S LA PUERTA ST 90023

Certificate Information: 1114 1/2 S LA PUERTA ST 90023

Application / Permit
22014-10000-00286
Plan Check / Job No.
B22LA01195
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO DETACHED GARAGE AND CONVERSION TO AN ADU.
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 12/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 JOE VO
Corrections Issued 1/29/2022 JOE VO
Plan Check Approved 3/7/2022 JOE VO
Issued 3/23/2022 APPLICANT
CofO in Progress 11/1/2023 PEDRO SIERRA
CofO in Progress 11/1/2023 PEDRO SIERRA
Permit Finaled 12/19/2023 DANIEL SANCHEZ
CofO Issued 12/19/2023 DANIEL SANCHEZ
Permit Finaled 12/19/2023 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 2/17/2022 CINDY QI
Roof/Waste drainage to street Cleared 2/17/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 2/22/2022 CINDY QI
Sewer availability Cleared 2/22/2022 CINDY QI

Contact Information

Contractor Garage To Apartment Inc General Construction; Lic. No.: 1041564-B 1102 SAN FERNANDO RD SUITE 206      SAN FERNANDO, CA 91340

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2022 No Access for Inspection JUAN ESCOTO DELGADO
Footing/Foundation/Slab 4/19/2022 Corrections Issued JUAN ESCOTO DELGADO
Footing/Foundation/Slab 4/28/2022 Approved JUAN ESCOTO DELGADO
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Approved JUAN ESCOTO DELGADO
Interior/Exterior Lathing 6/23/2022 Partial Approval JUAN ESCOTO DELGADO
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 No Access for Inspection JUAN ESCOTO DELGADO
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Corrections Issued JUAN ESCOTO DELGADO
ELECTRICAL-Rough 4/11/2023 Approved MARK VAN SLOOTEN
PLUMBING-Rough 4/11/2023 Corrections Issued MARK VAN SLOOTEN
Insulation 4/24/2023 Approved MARK VAN SLOOTEN
Drywall Nailing 5/1/2023 Approved MARK VAN SLOOTEN
Green Building Rough 5/1/2023 Approved MARK VAN SLOOTEN
BUILDING-Rough-Frame 7/27/2023 Approved MARK VAN SLOOTEN
Final 7/27/2023 Corrections Issued MARK VAN SLOOTEN
Green Building Final 7/27/2023 Approved MARK VAN SLOOTEN
MERV13>=Final 7/27/2023 Approved MARK VAN SLOOTEN
MERV13>=Rough 7/27/2023 Approved MARK VAN SLOOTEN
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Approved MARK VAN SLOOTEN
Smoke Detectors 7/27/2023 Approved MARK VAN SLOOTEN
ELECTRICAL-Final 9/20/2023 Corrections Issued PEDRO SIERRA
Final 9/20/2023 Corrections Issued PEDRO SIERRA
HVAC-Final 9/20/2023 Corrections Issued PEDRO SIERRA
PLUMBING-Final 9/20/2023 Corrections Issued PEDRO SIERRA
Final 10/18/2023 Corrections Issued PEDRO SIERRA
Final 10/30/2023 OK to Issue CofO PEDRO SIERRA
Service/Power Release 10/30/2023 Approved PEDRO SIERRA