3878 S WELLAND AVE 90008
Certificate Information: 3878 S WELLAND AVE 90008
- Application / Permit
- 22014-10000-00285
- Plan Check / Job No.
- B22LA01180
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION (343 SF) TO (E) 1-STORY SFD AND INTERIOR REMODEL.
- Permit Issued
- Issued on 3/31/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2022 | VIVIAN LAO |
| Corrections Issued | 1/27/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 2/15/2022 | CARLOS MONTES |
| Plan Check Approved | 2/25/2022 | VIVIAN LAO |
| Issued | 3/31/2022 | APPLICANT |
| CofO in Progress | 2/28/2023 | ANTHONY EGSON |
| Permit Finaled | 3/4/2023 | DEROLD HAUFF |
| CofO Issued | 3/4/2023 | DEROLD HAUFF |
| Permit Finaled | 3/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/15/2022 | CELINA MORENO |
| Sewer availability | Cleared | 2/15/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2022 | CELINA MORENO |
Contact Information
| Contractor | Valencia Construction Company; Lic. No.: 1015167-B | 12069 SMALLWOOD AVE DOWNEY, CA 90242 |
| Engineer | Rubio,, Ramon; Lic. No.: S6480 | 5842 WARWICK CIRCLE LA PALMA, CA 90623 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/23/2022 | No Access for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/24/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Approved | ANTHONY EGSON |
| Insulation | 6/24/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/1/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 8/4/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/11/2022 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 8/11/2022 | Partial Approval | ANTHONY EGSON |
| Insulation | 8/19/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/19/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 8/19/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/31/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 8/31/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/31/2022 | Approved | ANTHONY EGSON |
| Gas Test | 10/25/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/17/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/17/2023 | Approved | ANTHONY EGSON |
| Final | 1/17/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/17/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 1/17/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 1/17/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 1/17/2023 | Approved | ANTHONY EGSON |
| Smoke Detectors | 1/17/2023 | Approved | ANTHONY EGSON |
| Final | 1/24/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 2/28/2023 | OK to Issue CofO | ANTHONY EGSON |