884 W 2ND ST 90731

Certificate Information: 884 W 2ND ST 90731

Application / Permit
22014-10000-00232
Plan Check / Job No.
B22LA00943
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) UNDERFLOOR AREA OF (E) SFD TO STORAGE (745 SF) COMPLY WITH DEPARTMENT ORDER effective date 02/21/2012. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 6/17/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 VIVIAN LAO
Corrections Issued 2/1/2022 VIVIAN LAO
Quality Review Completed 2/2/2022 KEN GILL
Building Plans Picked Up 2/11/2022 APPLICANT
Applicant returned to address corrections 5/18/2022 VIVIAN LAO
Plan Check Approved 6/3/2022 VIVIAN LAO
Issued 6/17/2022 APPLICANT
CofO in Progress 10/24/2022 ANDREW BEELI
Permit Finaled 10/27/2022 BRUCE TODD
CofO Issued 10/27/2022 BRUCE TODD
Permit Finaled 10/27/2022 BRUCE TODD

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/29/2022 JOSE HERNANDEZ
Sewer availability Cleared 4/29/2022 JOSE HERNANDEZ
GPI Written Notices Cleared 6/3/2022 VIVIAN LAO
Grading Pre-Inspection Cleared 6/3/2022 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/23/2022 Corrections Issued ANDREW BEELI
Footing/Foundation/Slab 7/25/2022 Corrections Issued ANDREW BEELI
Excavation/Setback/Form/Re-Bar 8/10/2022 Approved ANDREW BEELI
Footing/Foundation/Slab 8/29/2022 Approved ANDREW BEELI
PLUMBING-Rough 8/29/2022 Approved ANDREW BEELI
BUILDING-Rough-Frame 9/1/2022 Approved ANDREW BEELI
Drywall Nailing 9/1/2022 Approved ANDREW BEELI
ELECTRICAL-Final 9/1/2022 Approved ANDREW BEELI
Final 9/1/2022 OK to Issue CofO ANDREW BEELI
Green Building Final 9/1/2022 Approved ANDREW BEELI
Green Building Rough 9/1/2022 Approved ANDREW BEELI
PLUMBING-Final 9/1/2022 Approved ANDREW BEELI
Reinforced Concrete Frame 9/1/2022 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved ANDREW BEELI
Smoke Detectors 9/1/2022 Approved ANDREW BEELI