9511 W NATIONAL BLVD 90034
Certificate Information: 9511 W NATIONAL BLVD 90034
- Application / Permit
- 22014-10000-00218
- Plan Check / Job No.
- B22LA00882
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1,150 S.F. ADDITION TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | JAD BASMA |
| Corrections Issued | 2/25/2022 | JAD BASMA |
| Quality Review Completed | 3/18/2022 | KEN GILL |
| Applicant returned to address corrections | 5/25/2022 | JAD BASMA |
| Building Plans Picked Up | 6/24/2022 | APPLICANT |
| Applicant returned to address corrections | 9/12/2022 | JAD BASMA |
| Plan Check Approved | 9/16/2022 | JAD BASMA |
| Plan Check Approved | 9/16/2022 | JAD BASMA |
| Plan Check Approved | 9/16/2022 | JAD BASMA |
| Issued | 9/16/2022 | APPLICANT |
| CofO in Progress | 6/11/2024 | ASHLEY THOMPSON |
| Permit Finaled | 6/11/2024 | DANIEL ORRANTE |
| CofO Issued | 6/11/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/11/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/14/2022 | CATHERINE ADROVER |
| Address approval | Cleared | 6/15/2022 | CATHERINE ADROVER |
| Address approval | Cleared | 6/15/2022 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 7/8/2022 | MICHAEL GILLISSIE |
| Low Impact Development | Cleared | 8/12/2022 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 8/25/2022 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 8/25/2022 | JAD BASMA |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2022 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 8/27/2022 | JOSE HERNANDEZ |
| ZI | Cleared | 8/30/2022 | CONNIE CHAUV |
Contact Information
| Contractor | Chase Construction Inc; Lic. No.: 700816-B | 1825 PANDORA AVE LOS ANGELES, CA 90025 |
| Contractor | Owner-Builder | , |
| Engineer | Estructura, Usa; Lic. No.: C4808 | 1205 PINE 201 LONG BEACH, CA 90813 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/28/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 9/29/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Inspection | 10/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 10/21/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 11/17/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 2/14/2023 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 2/16/2023 | Approved | ASHLEY THOMPSON |
| Deputy Wood Construction | 7/3/2023 | Conditional Approval | DAVID FEILER |
| Insulation | 7/5/2023 | Partial Approval | CLAYTON GRAHAM |
| Wood Frame | 7/5/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 7/19/2023 | Partial Approval | CLAYTON GRAHAM |
| HVAC-Rough | 7/19/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 8/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 8/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 8/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 8/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| MERV13>=Rough | 8/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 8/14/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/14/2023 | Partial Approval | JESUS PINEDA |
| Verify Sprinkler Sign Off | 8/14/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/18/2023 | Partial Approval | CLAYTON GRAHAM |
| Final | 8/18/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 8/18/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 8/18/2023 | Approved | CLAYTON GRAHAM |
| MERV13>=Rough | 8/18/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 8/31/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 9/8/2023 | Approved | BEN MOLSTAD |
| Shower Pan | 11/3/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 11/8/2023 | Approved | MEL KHACHATOURIAN |
| Sewer | 11/21/2023 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 12/6/2023 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 1/31/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/1/2024 | No Access for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/10/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 4/10/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 4/10/2024 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 4/12/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/12/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 6/10/2024 | OK to Issue CofO | ASHLEY THOMPSON |
| Green Building Final | 6/10/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 6/10/2024 | Approved | ASHLEY THOMPSON |