6201 N JACKIE AVE 91367
Certificate Information: 6201 N JACKIE AVE 91367
- Application / Permit
- 22014-10000-00200
- Plan Check / Job No.
- B22LA00835
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY W/ ATTACHED GARAGE **BUILDING TO BE FULLY SPRINKLERED BY NFPA-13D**
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Corrected on 4/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2022 | RAHEL BEYENE |
| Corrections Issued | 1/25/2022 | RAHEL BEYENE |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| Applicant returned to address corrections | 5/3/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 5/11/2022 | FERNANDO FLORES |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 4/12/2023 | TROY SANDERS |
| CofO Issued-Status Void | 4/18/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 4/18/2023 | JOHN JANSON |
| Re-Activate Permit | 4/26/2023 | JOHN JANSON |
| Permit Finaled | 4/27/2023 | JOHN JANSON |
| CofO Corrected | 4/27/2023 | JOHN JANSON |
| Permit Finaled | 4/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 2/8/2022 | AMIR KASHFI |
| Specific Plan | Cleared | 2/17/2022 | PETE EYRE |
| Low Impact Development | Cleared | 4/20/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 4/26/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/11/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 7/19/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 8/23/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 8/23/2022 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 8/29/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 8/29/2022 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Partial Approval | TROY SANDERS |
| HVAC-Rough | 8/29/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 8/29/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 8/29/2022 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 10/4/2022 | Partial Approval | TROY SANDERS |
| Special/Order Compliance | 10/4/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 10/28/2022 | Approved | TROY SANDERS |
| Green Building Rough | 10/28/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 11/28/2022 | Approved | TROY SANDERS |
| Insulation | 11/28/2022 | Approved | TROY SANDERS |
| Final | 2/10/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 2/10/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 2/10/2023 | Approved | DAVID SCANTLIN |
| Final | 4/6/2023 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Final | 4/6/2023 | Approved | HORACE FULTZ |
| Special/Order Compliance | 4/6/2023 | Partial Inspection | MORRIS JACKSON |
| Final | 4/12/2023 | OK to Issue CofO | TROY SANDERS |