345-347 S MCCADDEN PL 90020

Certificate Information: 345-347 S MCCADDEN PL 90020

Application / Permit
22014-10000-00188
Plan Check / Job No.
B22LA00757
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15'-0" X 13'-0" ADDITION AND CONVERT 6'-0" X 12'-4" PORTION OF SINGLE FMAILY DWELLING INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) AND REMODEL SINGLE FAMILY DWELLING - PER ENGINEER
Permit Issued
Issued on 3/28/2023
Issuing Office
Current Status
CofO Issued on 10/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 JOE VO
Corrections Issued 1/21/2022 JOE VO
Applicant returned to address corrections 3/9/2022 JOE VO
Applicant returned to address corrections 1/23/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/9/2023 TSE MING HUANG
Applicant returned to address corrections 2/10/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/13/2023 DANIEL ABRAMYAN
Plan Check Approved 2/22/2023 DANIEL ABRAMYAN
Issued 3/28/2023 APPLICANT
CofO in Progress 8/27/2024 RONNIE MINDANAO
CofO in Progress 9/6/2024 JOAQUIN GREENOUGH
CofO in Progress 10/1/2024 RONNIE MINDANAO
Permit Finaled 10/16/2024 RUBEN SALAS
CofO Issued 10/16/2024 RUBEN SALAS
Permit Finaled 10/16/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/29/2022 CINDY QI
Roof/Waste drainage to street Cleared 3/29/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/30/2022 CINDY QI
Sewer availability Cleared 3/30/2022 CINDY QI
Historic monument Cleared 10/5/2022 SUKI GERSHENHORN
HPOZ Cleared 12/5/2022 SUKI GERSHENHORN

Contact Information

Contractor Meckauer Design+Build Inc; Lic. No.: 462080-B       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/29/2024 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 2/16/2024 Corrections Issued AMIR NAZARIAN
METHANE-Barrier 2/16/2024 Not Ready for Inspection AMIR NAZARIAN
METHANE-Subgrade 2/16/2024 Not Ready for Inspection AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 2/21/2024 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 3/5/2024 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 3/5/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 3/5/2024 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Approved RONNIE MINDANAO
Insulation 3/12/2024 Partial Approval RONNIE MINDANAO
Wood Frame 3/12/2024 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 3/19/2024 Approved RONNIE MINDANAO
ELECTRICAL-Rough 4/17/2024 Approved RONNIE MINDANAO
HVAC-Rough 4/17/2024 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Corrections Issued RONNIE MINDANAO
Green Building Rough 5/7/2024 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 5/23/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Approved RONNIE MINDANAO
Green Building Rough 5/23/2024 Not Ready for Inspection RONNIE MINDANAO
Insulation 5/24/2024 Not Ready for Inspection JOSH MEISTER
Insulation 5/28/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 5/31/2024 Approved RONNIE MINDANAO
Drywall Nailing 5/31/2024 Not Ready for Inspection RONNIE MINDANAO
Green Building Final 5/31/2024 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 5/31/2024 Approved RONNIE MINDANAO
HVAC-Rough 5/31/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 6/3/2024 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 6/4/2024 Approved RONNIE MINDANAO
Shower Pan 6/4/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 6/6/2024 Partial Approval AMIR NAZARIAN
Drywall Nailing 8/6/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 8/6/2024 Corrections Issued RONNIE MINDANAO
Final 8/6/2024 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 8/6/2024 Approved RONNIE MINDANAO
Green Building Final 8/6/2024 Approved RONNIE MINDANAO
HVAC-Final 8/6/2024 Corrections Issued RONNIE MINDANAO
METHANE-Barrier 8/6/2024 Approved RONNIE MINDANAO
METHANE-Final 8/6/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 8/6/2024 Approved RONNIE MINDANAO
PLUMBING-Final 8/6/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV No Gas RONNIE MINDANAO
Smoke Detectors 8/6/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 8/16/2024 Approved RONNIE MINDANAO
Final 8/16/2024 Partial Approval RONNIE MINDANAO
HVAC-Final 8/16/2024 Approved RONNIE MINDANAO
Final 8/26/2024 Not Ready for Inspection RONNIE MINDANAO
Final 10/1/2024 OK to Issue CofO RONNIE MINDANAO