345-347 S MCCADDEN PL 90020
Certificate Information: 345-347 S MCCADDEN PL 90020
- Application / Permit
- 22014-10000-00188
- Plan Check / Job No.
- B22LA00757
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 15'-0" X 13'-0" ADDITION AND CONVERT 6'-0" X 12'-4" PORTION OF SINGLE FMAILY DWELLING INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) AND REMODEL SINGLE FAMILY DWELLING - PER ENGINEER
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Current Status
- CofO Issued on 10/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | JOE VO |
| Corrections Issued | 1/21/2022 | JOE VO |
| Applicant returned to address corrections | 3/9/2022 | JOE VO |
| Applicant returned to address corrections | 1/23/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/9/2023 | TSE MING HUANG |
| Applicant returned to address corrections | 2/10/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/13/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 2/22/2023 | DANIEL ABRAMYAN |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 8/27/2024 | RONNIE MINDANAO |
| CofO in Progress | 9/6/2024 | JOAQUIN GREENOUGH |
| CofO in Progress | 10/1/2024 | RONNIE MINDANAO |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
| CofO Issued | 10/16/2024 | RUBEN SALAS |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 3/29/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | CINDY QI |
| Sewer availability | Cleared | 3/30/2022 | CINDY QI |
| Historic monument | Cleared | 10/5/2022 | SUKI GERSHENHORN |
| HPOZ | Cleared | 12/5/2022 | SUKI GERSHENHORN |
Contact Information
| Contractor | Meckauer Design+Build Inc; Lic. No.: 462080-B | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 2/16/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Barrier | 2/16/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| METHANE-Subgrade | 2/16/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 2/21/2024 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/5/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 3/5/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 3/5/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Approved | RONNIE MINDANAO |
| Insulation | 3/12/2024 | Partial Approval | RONNIE MINDANAO |
| Wood Frame | 3/12/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 3/19/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/17/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 4/17/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 5/7/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 5/23/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 5/23/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 5/24/2024 | Not Ready for Inspection | JOSH MEISTER |
| Insulation | 5/28/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 5/31/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Final | 5/31/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 5/31/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 5/31/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 6/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 6/4/2024 | Approved | RONNIE MINDANAO |
| Shower Pan | 6/4/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 6/6/2024 | Partial Approval | AMIR NAZARIAN |
| Drywall Nailing | 8/6/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 8/6/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 8/6/2024 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/6/2024 | Approved | RONNIE MINDANAO |
| Green Building Final | 8/6/2024 | Approved | RONNIE MINDANAO |
| HVAC-Final | 8/6/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 8/6/2024 | Approved | RONNIE MINDANAO |
| METHANE-Final | 8/6/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 8/6/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 8/6/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV No Gas | RONNIE MINDANAO |
| Smoke Detectors | 8/6/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 8/16/2024 | Approved | RONNIE MINDANAO |
| Final | 8/16/2024 | Partial Approval | RONNIE MINDANAO |
| HVAC-Final | 8/16/2024 | Approved | RONNIE MINDANAO |
| Final | 8/26/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 10/1/2024 | OK to Issue CofO | RONNIE MINDANAO |