7226 S DENKER AVE 90047
Certificate Information: 7226 S DENKER AVE 90047
- Application / Permit
- 22014-10000-00186
- Plan Check / Job No.
- B22LA00732
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT EXISTING GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED STORAGE
- Permit Issued
- Issued on 7/18/2022
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2022 | SELLA BENYAMIN |
| Corrections Issued | 1/25/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 5/24/2022 | SELLA BENYAMIN |
| Plan Check Approved | 6/14/2022 | SELLA BENYAMIN |
| Issued | 7/18/2022 | APPLICANT |
| CofO in Progress | 7/12/2024 | MICHAEL LEWIS |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
| CofO Issued | 7/22/2024 | DEROLD HAUFF |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/19/2022 | RIDWAN HARDY |
| Address approval | Cleared | 5/25/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/6/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Final | 7/29/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 11/1/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 11/1/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 12/27/2022 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/12/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/26/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 9/26/2023 | Partial Inspection | MICHAEL LEWIS |
| HVAC-Final | 9/26/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 9/26/2023 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 9/26/2023 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 10/11/2023 | Approved | MICHAEL LEWIS |
| Rough-Elec/Plmb/HVAC | 1/16/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 4/8/2024 | Partial Inspection | MICHAEL LEWIS |
| Insulation | 4/8/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/4/2024 | Approved | MICHAEL LEWIS |
| Sewer | 6/4/2024 | Approved | MICHAEL LEWIS |
| Final | 6/6/2024 | Conditional Approval | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Approved | MICHAEL LEWIS |
| Sewer | 6/6/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 6/6/2024 | Approved | MICHAEL LEWIS |
| Final | 6/21/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 7/11/2024 | OK to Issue CofO | MICHAEL LEWIS |