22039 W VICTORY BLVD 91303

Certificate Information: 22039 W VICTORY BLVD 91303

Application / Permit
22014-10000-00161
Plan Check / Job No.
B22LA00614
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SINGLE FAMILY DWELLING FOR NEW BATH AND WALK-IN CLOSET. REMODEL EXISTING BEDROOMS.
Permit Issued
Issued on 2/26/2022
Issuing Office
Current Status
CofO Issued on 3/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2022 JOSEPH RAFOLS
Corrections Issued 1/20/2022 JOSEPH RAFOLS
Plan Check Approved 2/7/2022 GEORGE ALVAREZ
Building Plans Picked Up 2/17/2022 APPLICANT
Issued 2/26/2022 APPLICANT
CofO in Progress 7/6/2022 TROY SANDERS
Permit Finaled 3/11/2023 DANIEL ORRANTE
CofO Issued 3/11/2023 DANIEL ORRANTE
Permit Finaled 3/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/22/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/22/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/25/2022 DAGOVERTO GUERRERO
ZI Cleared 1/25/2022 MIGUEL GAMBOA

Contact Information

Contractor Akr Construction Inc; Lic. No.: 1065837-B 22039 VICTORY BLVD      WOODLAND HILLS, CA 91303
Engineer Sin,, John P; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/14/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval TROY SANDERS
PLUMBING-Rough 3/23/2022 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Partial Approval TROY SANDERS
Interior/Exterior Lathing 4/6/2022 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 4/13/2022 Partial Inspection JESUS PINEDA
BUILDING-Rough-Frame 4/18/2022 Approved TROY SANDERS
ELECTRICAL-Rough 4/18/2022 Approved TROY SANDERS
PLUMBING-Rough 4/18/2022 Approved TROY SANDERS
Insulation 4/25/2022 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 4/25/2022 Not Ready for Inspection JESUS PINEDA
Insulation 4/27/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 4/27/2022 Partial Approval JESUS PINEDA
Drywall Nailing 5/2/2022 Approved JUSTIN HAWLEY
Shower Pan 5/5/2022 Approved TROY SANDERS
Interior/Exterior Lathing 5/10/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 7/5/2022 Approved TROY SANDERS
Final 7/5/2022 OK to Issue CofO TROY SANDERS
Green Building Final 7/5/2022 Approved TROY SANDERS
Green Building Rough 7/5/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/5/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 7/5/2022 Approved TROY SANDERS