519 E 65TH ST 90003

Certificate Information: 519 E 65TH ST 90003

Application / Permit
22014-10000-00136
Plan Check / Job No.
B22LA00520
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[25'-8" x 21'-1"] IRREGULAR ADDITION AT REAR OF EXISTING SINGLE FAMILY DWELLING FOR (2) NEW BEDROOMS. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 3/18/2022
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 GEORGE ALVAREZ
Corrections Issued 1/26/2022 GEORGE ALVAREZ
Building Plans Picked Up 2/4/2022 APPLICANT
Applicant returned to address corrections 3/9/2022 GEORGE ALVAREZ
Plan Check Approved 3/16/2022 GEORGE ALVAREZ
Issued 3/18/2022 APPLICANT
CofO in Progress 1/5/2023 LILIANA PORTILLO
Permit Finaled 1/19/2023 DEROLD HAUFF
CofO Issued 1/19/2023 DEROLD HAUFF
Permit Finaled 1/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/22/2022 ABEL CASILLAS
Roof/Waste drainage to street Cleared 2/22/2022 ABEL CASILLAS
Sewer availability Cleared 2/22/2022 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,
Engineer Mokri-Arganeh,, Fattaneh; Lic. No.: C52608 2075 S COUNTRY CYN RD      HACIENDA HEIGHTS, CA 91745

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/21/2022 Approved HORACE FULTZ
Footing/Foundation/Slab 7/26/2022 Approved ADAM ESCOTO
BUILDING-Rough-Frame 8/5/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 8/5/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Partial Approval LILIANA PORTILLO
Insulation 8/9/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 9/7/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 9/7/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 9/15/2022 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 9/15/2022 Approved LILIANA PORTILLO
Green Building Rough 9/15/2022 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 9/15/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 9/15/2022 Approved LILIANA PORTILLO
Insulation 9/20/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/20/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 9/26/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/26/2022 Partial Approval LILIANA PORTILLO
Shower Pan 9/26/2022 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 9/30/2022 Approved LILIANA PORTILLO
Shower Pan 9/30/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Not Ready ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/16/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/16/2022 Corrections Issued LILIANA PORTILLO
Final 11/16/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 11/16/2022 Corrections Issued LILIANA PORTILLO
Green Building Rough 11/16/2022 Approved LILIANA PORTILLO
HVAC-Final 11/16/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 11/16/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 11/16/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 12/14/2022 Approved LILIANA PORTILLO
Final 12/14/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 12/14/2022 Approved LILIANA PORTILLO
HVAC-Final 12/14/2022 Approved LILIANA PORTILLO
PLUMBING-Final 12/14/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 12/14/2022 Approved LILIANA PORTILLO
Final 1/4/2023 OK to Issue CofO LILIANA PORTILLO