12310 N LITHUANIA DR 91344

Certificate Information: 12310 N LITHUANIA DR 91344

Application / Permit
22014-10000-00116
Plan Check / Job No.
B22LA00430
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ATTACHED 500 SQFT REC ROOM TO EXISTING SFD AND COVERED PATIO (180 SQFT)
Permit Issued
Issued on 8/3/2022
Issuing Office
Current Status
CofO Issued on 5/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2022 APPLICANT
Assigned to Plan Check Engineer 2/8/2022 JAD BASMA
Corrections Issued 2/11/2022 JAD BASMA
Quality Review Completed 2/16/2022 KEN GILL
Building Plans Picked Up 2/25/2022 APPLICANT
Plan Check Approved 8/3/2022 JAD BASMA
Issued 8/3/2022 APPLICANT
CofO in Progress 7/28/2023 SEAN WIRCH
CofO in Progress 3/7/2024 SEAN WIRCH
CofO in Progress 3/8/2024 JOHN JANSON
Permit Finaled 5/10/2024 DANIEL ORRANTE
CofO Issued 5/10/2024 DANIEL ORRANTE
Permit Finaled 5/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/8/2022 LEE GUILBEAUX
Address approval Cleared 3/8/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/8/2022 LEE GUILBEAUX
Sewer availability Cleared 3/8/2022 LEE GUILBEAUX
Low Impact Development Cleared 7/8/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 7/15/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 8/3/2022 JAD BASMA
Grading Pre-Inspection Cleared 8/3/2022 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/25/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/1/2022 Corrections Issued SEAN WIRCH
ELECTRICAL-Rough 11/1/2022 Approved SEAN WIRCH
Final 11/1/2022 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Approved SEAN WIRCH
Green Building Rough 11/1/2022 Approved SEAN WIRCH
HVAC-Rough 11/1/2022 Approved SEAN WIRCH
PLUMBING-Rough 11/1/2022 Approved SEAN WIRCH
ELECTRICAL-Rough 11/2/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Approved DAVID SCANTLIN
HVAC-Rough 11/2/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 11/2/2022 Approved DAVID SCANTLIN
Insulation 11/7/2022 Not Ready for Inspection JUSTIN HAWLEY
Interior/Exterior Lathing 11/7/2022 Not Ready for Inspection JUSTIN HAWLEY
Drywall Nailing 11/8/2022 Approved KRISTEN CAUSEY
Insulation 11/8/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/8/2022 Partial Inspection KRISTEN CAUSEY
Shower Pan 11/22/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 7/31/2023 Approved SEAN WIRCH
Final 7/31/2023 OK to Issue CofO SEAN WIRCH
Footing/Foundation/Slab 7/31/2023 Approved SEAN WIRCH
Green Building Final 7/31/2023 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved SEAN WIRCH
Smoke Detectors 7/31/2023 Approved SEAN WIRCH