1636 N LEMOYNE ST 90026
Certificate Information: 1636 N LEMOYNE ST 90026
- Application / Permit
- 22014-10000-00095
- Plan Check / Job No.
- B22LA00358
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW GROUND FLOOR & 2ND FLOOR ADDITON TO (E) ONE STORY SINGLE FAMILY DWELLING & MAJOR REMODEL .
- Permit Issued
- Issued on 1/2/2024
- Issuing Office
- Metro
- Current Status
- Issued on 1/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | GARO TELMI |
| Corrections Issued | 2/9/2022 | GARO TELMI |
| Quality Review Completed | 2/16/2022 | KEN GILL |
| Building Plans Picked Up | 2/22/2022 | APPLICANT |
| Applicant returned to address corrections | 7/26/2022 | GARO TELMI |
| Applicant returned to address corrections | 8/9/2022 | GARO TELMI |
| Applicant returned to address corrections | 8/11/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/22/2022 | GARO TELMI |
| Applicant returned to address corrections | 12/20/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/6/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/11/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/28/2023 | GARO TELMI |
| Plan Check Approved | 8/9/2023 | GARO TELMI |
| Issued | 1/2/2024 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/22/2022 | RICARDO BOHORQUEZ |
| BHO/Hillside ordinance | Cleared | 3/23/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 3/23/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 3/23/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 3/23/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 3/23/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 4/5/2022 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/5/2023 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 1/6/2023 | AMMAR ELTAWIL |
| Work Adjacent to Public Way | Cleared | 2/13/2023 | JOSE RODRIGUEZ |
| Roof/Waste drainage to street | Cleared | 3/24/2023 | CELINA MORENO |
| GPI Written Notices | Cleared | 8/9/2023 | ROBERT HUGHES |
Contact Information
| Architect | , ; Lic. No.: C33622 | 1636 LEMOYN ST LA, CA 90026 |
| Contractor | Williams Christopher; Lic. No.: 711380-B | P O BOX 8652 LA CRESCENTA, CA 91224 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Cugno,, Giuseppe; Lic. No.: EG1804 | 1461 E CHEVY CHASE DR 200 BYER GEOTECHNICAL, INC. GLENDALE, CA 91206 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/13/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 3/6/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/13/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 4/22/2024 | Partial Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 9/23/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Corrections Issued | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/28/2024 | Corrections Issued | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Partial Approval | ROY SPAULDING |
| HVAC-Rough | 10/28/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 11/19/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/19/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/2/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 12/2/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 12/2/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/22/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 1/22/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/22/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/22/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 1/22/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/10/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/10/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 4/2/2025 | No Access for Inspection | JOSH MEISTER |
| Insulation | 4/28/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 5/15/2025 | Approved | ALEX COLIN |
| Shower Pan | 8/11/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 8/13/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/27/2025 | Partial Approval | ALEX COLIN |
| Interior/Exterior Lathing | 9/18/2025 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/16/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/6/2026 | No Access for Inspection | HAMIK HARTOUNIAN |