365 1/2 W SEPULVEDA ST 90731

Certificate Information: 365 1/2 W SEPULVEDA ST 90731

Application / Permit
22014-10000-00082
Plan Check / Job No.
B22LA00315
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT PORTION OF (E) DETACHED GARAGE TO ADU AND GROUND FLOOR ADDITION TO ADU PER LAMC 12.22.A.33(c)-(d). 1 BED 1 BATH
Permit Issued
Issued on 7/11/2022
Issuing Office
Current Status
CofO Issued on 4/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 JOE VO
Corrections Issued 1/13/2022 VIVIAN LAO
Applicant returned to address corrections 2/25/2022 JOE VO
Applicant returned to address corrections 7/1/2022 JOE VO
Plan Check Approved 7/7/2022 JOE VO
Issued 7/11/2022 APPLICANT
CofO in Progress 4/9/2024 EUGENE CASSIDY
Permit Finaled 4/10/2024 ANSON MAGLASANG
CofO Issued 4/10/2024 ANSON MAGLASANG
Permit Finaled 4/10/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/4/2022 HUGO LOPEZ
Roof/Waste drainage to street Cleared 4/4/2022 HUGO LOPEZ
Historic Resource Verification Cleared 4/5/2022 MAX LODER
Eng Process Fee Ord 176,300 Cleared 4/12/2022 HUGO LOPEZ
Sewer availability Cleared 4/12/2022 HUGO LOPEZ
Community Plan Implem. Overlay Cleared 5/6/2022 NORALI MARTINEZ
Redevelopment Project Area Cleared 5/11/2022 GRACIELA ACOSTA
Tenant Habitability Plan Cleared 5/18/2022 ISMAEL HERNANDEZ
Grading Pre-Inspection Cleared 7/7/2022 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Latifian,, Amirmasoud; Lic. No.: C87552 13075 PACIFIC PROMENADE 317      PLAYA VISTA, CA 90094

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/4/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 8/25/2022 Partial Approval ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 9/7/2022 Corrections Issued ANSON MAGLASANG
Gas Test 4/24/2023 Corrections Issued ANSON MAGLASANG
Underground Mechanical 4/24/2023 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Rough 5/1/2023 Partial Approval EUGENE CASSIDY
Gas Test 5/1/2023 Approved EUGENE CASSIDY
Sewer 5/1/2023 Approved EUGENE CASSIDY
Underground Mechanical 5/1/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/15/2023 Approved JAMES CHAVEZ
Drywall Nailing 5/15/2023 Approved JAMES CHAVEZ
Final 5/15/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 5/15/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 5/15/2023 Approved JAMES CHAVEZ
Final 5/19/2023 Corrections Issued ANSON MAGLASANG
Final 6/7/2023 Corrections Issued JAMES CHAVEZ
Final 1/22/2024 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 2/26/2024 Approved EUGENE CASSIDY
Final 4/8/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 4/8/2024 Approved EUGENE CASSIDY
PLUMBING-Final 4/8/2024 Approved EUGENE CASSIDY