421-423 S HIGHLAND AVE 90036

Certificate Information: 421-423 S HIGHLAND AVE 90036

Application / Permit
22014-10000-00081
Plan Check / Job No.
B22LA00305
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO REAR FOR SFD FOR NEW ADU. REMODEL SFD.
Permit Issued
Issued on 9/13/2022
Issuing Office
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 JOE VO
Corrections Issued 1/23/2022 JOE VO
Quality Review Completed 1/24/2022 LIPING TENG
Plan Check Approved 5/9/2022 JOE VO
Issued 9/13/2022 APPLICANT
CofO in Progress 9/28/2023 RICHARD DOCKUS
Permit Finaled 10/4/2023 DEROLD HAUFF
CofO Issued 10/4/2023 DEROLD HAUFF
Permit Finaled 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/26/2022 KHOUNG LE
Sewer availability Cleared 2/8/2022 KHOUNG LE
HPOZ Cleared 2/14/2022 SUKI GERSHENHORN
Historic monument Cleared 2/14/2022 SUKI GERSHENHORN
Construction near power lines Cleared 2/16/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 3/14/2022 KHOUNG LE
Low Impact Development Cleared 3/14/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/14/2022 KHOUNG LE

Contact Information

Architect Woodcraft,, Astra E; Lic. No.: NA32722       ,
Contractor Modline Builders Inc; Lic. No.: 1036403-B       ,
Engineer Tan,, Henreik Steven; Lic. No.: NA65723       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/29/2022 Partial Approval RICHARD DOCKUS
Sewer 11/29/2022 Approved RICHARD DOCKUS
METHANE-Subgrade 11/30/2022 Approved RICHARD DOCKUS
METHANE-Barrier 12/6/2022 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 12/8/2022 Approved RICHARD DOCKUS
Footing/Foundation/Slab 12/8/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 2/1/2023 Approved RICHARD DOCKUS
Shower Pan 2/15/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/29/2023 Partial Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/29/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 3/29/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 3/29/2023 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 3/29/2023 Approved ALIZAH MAYAGOITIA
METHANE-Rough 3/29/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/30/2023 Approved SCOTT FINNILA
ELECTRICAL-Rough 3/30/2023 Approved SCOTT FINNILA
ELECTRICAL-Rough 3/30/2023 Off-Hour Fees Due
Green Building Rough 3/30/2023 Approved SCOTT FINNILA
HVAC-Rough 3/30/2023 Approved SCOTT FINNILA
HVAC-Rough 3/30/2023 Off-Hour Fees Due
Special/Order Compliance 3/30/2023 Corrections Issued SCOTT FINNILA
Insulation 4/13/2023 Approved RICHARD DOCKUS
Drywall Nailing 5/1/2023 Approved RICHARD DOCKUS
ELECTRICAL-Final 9/18/2023 Not Ready for Inspection RICHARD DOCKUS
HVAC-Final 9/18/2023 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Final 9/21/2023 Approved RICHARD DOCKUS
HVAC-Final 9/21/2023 Approved RICHARD DOCKUS
PLUMBING-Final 9/21/2023 Approved RICHARD DOCKUS
Final 9/26/2023 OK to Issue CofO RICHARD DOCKUS
Green Building Final 9/26/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 9/26/2023 Approved RICHARD DOCKUS