8507 S CROYDON AVE 90045
Certificate Information: 8507 S CROYDON AVE 90045
- Application / Permit
- 22014-10000-00071
- Plan Check / Job No.
- B22LA00246
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PATIO COVER TO BE PART OF THE (E) SFD, ADDITION TO (E) SFD, AND INTERIOR REMODEL.
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2022 | FERNANDO FLORES |
| Corrections Issued | 1/12/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 3/30/2022 | AUNG SOE |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| Applicant returned to address corrections | 4/29/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 5/19/2022 | CRISTINA SALAZAR |
| Plan Check Approved | 5/27/2022 | MINA HABILI |
| Issued | 6/10/2022 | APPLICANT |
| CofO in Progress | 6/12/2024 | BOBBY KEY |
| Permit Finaled | 6/15/2024 | DANIEL ORRANTE |
| CofO Issued | 6/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/11/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 5/12/2022 | CATHERINE ADROVER |
Contact Information
| Architect | Andrew, Nunez; Lic. No.: C38110 | 6600 WARNER AVE 98 HUNTINGTON BEACH, CA 92647 |
| Contractor | Owner-Builder | , |
| Engineer | Singer,, Joanne Chapin; Lic. No.: C26900 | 40530 KINSALE PL INDIO, CA 92203 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/24/2022 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 6/30/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2022 | Corrections Issued | HERBERT GIRON |
| Sewer | 7/18/2022 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 9/26/2022 | Partial Approval | BOBBY KEY |
| Wood Frame | 9/27/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Corrections Issued | HERBERT GIRON |
| Deputy Wood Construction | 12/16/2022 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 3/2/2023 | Conditional Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 3/2/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/2/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/2/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/8/2023 | Approved | BOBBY KEY |
| Green Building Rough | 3/8/2023 | Approved | BOBBY KEY |
| Insulation | 3/8/2023 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 3/16/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 3/16/2023 | Partial Inspection | JESUS PINEDA |
| Shower Pan | 3/24/2023 | Approved | BOBBY KEY |
| Service/Power Release | 4/3/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/5/2023 | Approved | BOBBY KEY |
| Final | 5/18/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 9/28/2023 | Corrections Issued | BOBBY KEY |
| Final | 9/28/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/28/2023 | Approved | BOBBY KEY |
| HVAC-Final | 9/28/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/28/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 9/28/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/21/2024 | Approved | BOBBY KEY |
| Final | 5/21/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/21/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/21/2024 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Not Ready | BOBBY KEY |
| Final | 6/6/2024 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 6/6/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 6/6/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | BOBBY KEY |
| Final | 6/10/2024 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 6/10/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 6/10/2024 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Approved | BOBBY KEY |
| Final | 6/11/2024 | OK to Issue CofO | BOBBY KEY |