2012 1/2 W FAIR PARK AVE 90041

Certificate Information: 2012 1/2 W FAIR PARK AVE 90041

Application / Permit
22014-10000-00047
Plan Check / Job No.
B22LA00160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NFPA13D FIRE SPRINKLERS REQUIRED. CONVERT LOWER LEVEL PARKING GARAGE INTO AN ADU.
Permit Issued
Issued on 7/21/2022
Issuing Office
Current Status
CofO Issued on 4/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 JOE VO
Corrections Issued 1/29/2022 JOE VO
Applicant returned to address corrections 3/3/2022 JOE VO
Plan Check Approved 6/13/2022 JOE VO
Issued 7/21/2022 APPLICANT
CofO in Progress 4/5/2024 CRAIG VAUGHAN
No Progress 4/8/2024 CHARLES BOGHOSKHAN
CofO in Progress 4/8/2024 CHARLES BOGHOSKHAN
Permit Finaled 4/9/2024 DEROLD HAUFF
CofO Issued 4/9/2024 DEROLD HAUFF
Permit Finaled 4/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/2/2022 JEANIE LAM
Sewer availability Cleared 3/2/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/7/2022 JEANIE LAM
Tenant Habitability Plan Cleared 4/19/2022 MICHAEL SOTO
Grading Pre-Inspection Cleared 6/8/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2023 Approved CRAIG VAUGHAN
Pre-Inspection 3/14/2023 Corrections Issued CRAIG VAUGHAN
Wood Frame 7/31/2023 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 8/21/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 8/21/2023 Partial Approval CRAIG VAUGHAN
Verify Sprinkler Sign Off 8/21/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 8/28/2023 Approved CRAIG VAUGHAN
Smoke Detectors 8/28/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 9/8/2023 No Access for Inspection CRAIG VAUGHAN
Wood Frame 9/8/2023 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 9/14/2023 Partial Approval ROY SPAULDING
Green Building Rough 9/14/2023 Partial Approval ROY SPAULDING
Interior/Exterior Lathing 9/27/2023 Partial Approval CRAIG VAUGHAN
Wood Frame 9/27/2023 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 10/31/2023 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/7/2023 Approved CRAIG VAUGHAN
Green Building Rough 11/7/2023 Approved CRAIG VAUGHAN
HVAC-Rough 11/7/2023 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 11/7/2023 Approved CRAIG VAUGHAN
Insulation 11/9/2023 Approved CRAIG VAUGHAN
Drywall Nailing 11/16/2023 Not Ready for Inspection CRAIG VAUGHAN
Drywall Nailing 11/28/2023 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 11/30/2023 Corrections Issued CRAIG VAUGHAN
Drywall Nailing 12/7/2023 Approved CRAIG VAUGHAN
Final 1/29/2024 Corrections Issued CRAIG VAUGHAN
Green Building Final 1/29/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 1/29/2024 Approved CRAIG VAUGHAN
Final 3/7/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 4/2/2024 Conditional Approval CRAIG VAUGHAN
Final 4/4/2024 OK to Issue CofO CRAIG VAUGHAN