12883 W CORCORAN ST 91340
Certificate Information: 12883 W CORCORAN ST 91340
- Application / Permit
- 22014-10000-00025
- Plan Check / Job No.
- B22LA00077
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU WITH ADDITION.DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 5/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | JESSE JIMENEZ |
| Corrections Issued | 1/18/2022 | JESSE JIMENEZ |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
| Plan Check Approved | 9/2/2022 | DANIEL SANJUAN |
| Issued | 5/15/2023 | APPLICANT |
| CofO in Progress | 5/8/2025 | MICHEL ABAJAN |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | WALLIE JONG |
| Sewer availability | Cleared | 2/7/2022 | WALLIE JONG |
| Low Impact Development | Cleared | 4/29/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/31/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 8/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schaefer,, Jeffrey Ambrose; Lic. No.: C91734 | 3325 E 4TH ST LONG BEACH, CA 90814 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/28/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/2/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/12/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/12/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/12/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/12/2024 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 3/12/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/12/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/20/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/28/2024 | Approved | MICHEL ABAJAN |
| Insulation | 3/28/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/5/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/5/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/23/2024 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 6/10/2024 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/9/2024 | Approved | MICHEL ABAJAN |
| Final | 8/9/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 8/9/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 8/9/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 8/9/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/9/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 8/9/2024 | Approved | MICHEL ABAJAN |
| Final | 2/13/2025 | Corrections Issued | MICHEL ABAJAN |
| Final | 5/7/2025 | OK to Issue CofO | MICHEL ABAJAN |