8874 N MOREHART AVE 91352
Certificate Information: 8874 N MOREHART AVE 91352
- Application / Permit
- 22014-10000-00019
- Plan Check / Job No.
- B22LA00073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT REAR AND SIDE TO EXISTING ONE STORY SINGLE FAMILY DEWLLING
- Permit Issued
- Issued on 8/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2022 | TSE MING HUANG |
| Corrections Issued | 1/12/2022 | TSE MING HUANG |
| Building Plans Picked Up | 2/2/2022 | APPLICANT |
| Plan Check Approved | 7/29/2022 | AUNG SOE |
| Issued | 8/1/2022 | APPLICANT |
| CofO in Progress | 12/23/2022 | MATTHEW NELSON |
| CofO Issued | 1/9/2023 | RONALD MYRICK |
| Permit Finaled | 1/9/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 2/18/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/18/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Casillas,, Rafael Ortega; Lic. No.: C68234 | 1937 S BRADSHAWE AVE MONTEREY PARK, CA 91754 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 8/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/19/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/24/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 10/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 10/17/2022 | No Result Entered | ADRIAN GAUTHIER |
| Insulation | 10/20/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/20/2022 | Partial Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 11/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 11/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Shower Pan | 11/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 11/22/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/23/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 12/23/2022 | Approved | MATTHEW NELSON |
| Final | 12/23/2022 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 12/23/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 12/23/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 12/23/2022 | Approved | MATTHEW NELSON |
| MERV13>=Final | 12/23/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/23/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 12/23/2022 | Approved | MATTHEW NELSON |
| Pre-Inspection | 12/29/2022 | Approved | MATTHEW NELSON |