5631 N TOBIAS AVE 91411

Certificate Information: 5631 N TOBIAS AVE 91411

Application / Permit
22014-10000-00012
Plan Check / Job No.
B22LA00046
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING AND NEW ATTACHED PATIO.
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
Issued on 5/31/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/3/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 KHEDER ALRAZAA
Corrections Issued 1/16/2022 KHEDER ALRAZAA
Quality Review Completed 1/26/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/31/2022 APPLICANT
Plan Check Approved 5/10/2022 KHEDER ALRAZAA
Issued 5/31/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 3/1/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/2/2022 CARLOS AGUILERA
Low Impact Development Cleared 4/28/2022 KHAING AYE
Roof/Waste drainage to street Cleared 4/29/2022 CARLOS AGUILERA

Contact Information

Contractor Az Vision Remodeling; Lic. No.: 1015050-B 11909 TIARA STREET      VALLEY VILLAGE, CA 91607
Engineer Tuna,, Suleyman; Lic. No.: C73294 3332 BENNETT DRIVE      LOS ANGELES, CA 90068

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2022 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 7/22/2022 Not Ready for Inspection ARAM AVEDISIAN
Deputy Wood Construction 8/11/2022 Conditional Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 1/23/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 1/23/2023 Approved RYAN SALAZAR
HVAC-Rough 1/23/2023 Approved RYAN SALAZAR
PLUMBING-Rough 1/23/2023 Approved RYAN SALAZAR
Insulation 1/31/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/31/2023 Approved RYAN SALAZAR
Shower Pan 1/31/2023 Approved RYAN SALAZAR
Drywall Nailing 2/3/2023 Approved RYAN SALAZAR
Green Building Rough 2/3/2023 Approved RYAN SALAZAR
Shower Pan 2/28/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 4/19/2024 Not Ready for Inspection RYAN SALAZAR
Final 4/19/2024 Corrections Issued RYAN SALAZAR
HVAC-Final 4/19/2024 Not Ready for Inspection RYAN SALAZAR
Service/Power Release 4/19/2024 Not Ready for Inspection RYAN SALAZAR