1609 W 22ND ST 90732

Certificate Information: 1609 W 22ND ST 90732

Application / Permit
22014-10000-00011
Plan Check / Job No.
B22LA00037
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel throughout dwelling to remove load bearing walls at kitchen and living room area. Remodel of bedroom and bathrooms. Addition to enlarge master bathroom.
Permit Issued
Issued on 7/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2022 RICARDO RAMIREZ
Corrections Issued 1/13/2022 RICARDO RAMIREZ
Applicant returned to address corrections 2/20/2022 FARSHAD ALIMOHAMADI
Building Plans Picked Up 2/24/2022 APPLICANT
Plan Check Approved 3/12/2022 FERNANDO FLORES
Issued 7/7/2022 APPLICANT
CofO in Progress 2/18/2025 JOSEPH MCGARRY
CofO Issued 2/19/2025 ANSON MAGLASANG
Permit Finaled 2/19/2025 ANSON MAGLASANG

Permit Application Clearance Information

ZA Case Cleared 1/25/2022 RICHARD REASER
Roof/Waste drainage to street Cleared 1/26/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 2/1/2022 JOSE HERNANDEZ
Grading Pre-Inspection Cleared 2/24/2022 VASIL MIHALEV

Contact Information

Architect Song,, Michael; Lic. No.: C32566 5608 E PEABODY STREET      LONG BEACH, CA 90808
Contractor 7 Point Construction Inc; Lic. No.: 1015778-B 201 COVINA AVE SUITE 4      LONG BEACH, CA 90803
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/11/2022 Corrections Issued ANSON MAGLASANG
PLUMBING-Rough 7/11/2022 Partial Approval ANSON MAGLASANG
Footing/Foundation/Slab 7/14/2022 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Rough 8/25/2022 Partial Approval ANSON MAGLASANG
HVAC-Rough 8/25/2022 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 8/25/2022 Partial Approval ANSON MAGLASANG
Deputy Wood Construction 8/29/2022 Conditional Approval ANSON MAGLASANG
BUILDING-Rough-Frame 9/2/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 9/2/2022 Approved EUGENE CASSIDY
Green Building Rough 9/2/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 9/2/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 9/2/2022 Approved EUGENE CASSIDY
Insulation 9/9/2022 Approved ANSON MAGLASANG
Drywall Nailing 10/6/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 10/6/2022 Not Ready for Inspection ANSON MAGLASANG
Interior/Exterior Lathing 10/19/2022 Partial Approval ANSON MAGLASANG
Shower Pan 10/19/2022 Approved ANSON MAGLASANG
Gas Test 1/3/2023 Approved JOHN KLARIN
Service/Power Release 1/3/2023 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 3/21/2023 Approved JAMES CHAVEZ
Final 3/21/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 3/21/2023 Approved JAMES CHAVEZ
Green Building Final 3/21/2023 Corrections Issued JAMES CHAVEZ
Green Building Rough 3/21/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 3/21/2023 Approved JAMES CHAVEZ
Final 4/12/2023 Not Ready for Inspection ANSON MAGLASANG
Green Building Final 4/12/2023 Approved ANSON MAGLASANG
Final 1/27/2025 Corrections Issued JOSEPH MCGARRY
Final 2/6/2025 Not Ready for Inspection JOSEPH MCGARRY
Final 2/18/2025 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 2/18/2025 Approved JOSEPH MCGARRY