1525 N CAMPUS ROAD 90042
Certificate Information: 1525 N CAMPUS ROAD 90042
- Application / Permit
- 22014-10000-00008
- Plan Check / Job No.
- B22LA00031
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAIN HOUSE INTERIOR RMEODEL AND 110 SQ.FT. ADDITION AT FRONT. NEW KITCHEN, ADD BATH, NEW WINDOWS, ETC.
- Permit Issued
- Issued on 4/8/2022
- Issuing Office
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2022 | GEORGE ALVAREZ |
| Corrections Issued | 1/18/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 2/20/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/1/2022 | JOSEPH RAFOLS |
| Issued | 4/8/2022 | APPLICANT |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| CofO in Progress | 3/8/2023 | CRAIG VAUGHAN |
| Permit Finaled | 3/10/2023 | DEROLD HAUFF |
| CofO Issued | 3/10/2023 | DEROLD HAUFF |
| Permit Finaled | 3/10/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | CINDY QI |
| Sewer availability | Cleared | 1/21/2022 | CINDY QI |
| Grading Pre-Inspection | Cleared | 2/23/2022 | GEORGE ALVAREZ |
Contact Information
| Architect | Cooke,, Barrett H; Lic. No.: C37365 | 5239 WINDERMERE AVE LOS ANGELES, CA 90041 |
| Contractor | Jas General Construction; Lic. No.: 1026356-B | 7858 PHLOX ST DOWNEY, CA 90241 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/29/2022 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/5/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/12/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/2/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/13/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/13/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | No Access for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/21/2022 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 9/21/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/21/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/30/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 9/30/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 9/30/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 10/4/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 10/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 10/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 10/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 10/13/2022 | Approved | CHARLES BOGHOSKHAN |
| Final | 3/3/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 3/3/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 3/3/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/7/2023 | Approved | CRAIG VAUGHAN |
| Final | 3/7/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 3/7/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 3/7/2023 | Approved | CRAIG VAUGHAN |