1527 N CAMPUS ROAD 90042

Certificate Information: 1527 N CAMPUS ROAD 90042

Application / Permit
22014-10000-00006
Plan Check / Job No.
B22LA00030
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ADU WITH ADDITION TO CREATE ONE BEDROOM ONE BATH ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 4/8/2022
Issuing Office
Current Status
CofO Issued on 3/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2022 APPLICANT
Assigned to Plan Check Engineer 1/11/2022 RACHEL BEYENE
Corrections Issued 1/11/2022 RACHEL BEYENE
Plan Check Approved 2/22/2022 RICARDO RAMIREZ
Building Plans Picked Up 2/23/2022 APPLICANT
Issued 4/8/2022 APPLICANT
CofO in Progress 3/6/2023 CRAIG VAUGHAN
Permit Finaled 3/9/2023 DEROLD HAUFF
CofO Issued 3/9/2023 DEROLD HAUFF
Permit Finaled 3/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/18/2022 CINDY QI
Roof/Waste drainage to street Cleared 1/18/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/19/2022 CINDY QI
Sewer availability Cleared 1/19/2022 CINDY QI
Grading Pre-Inspection Cleared 2/22/2022 RAHEL BEYENE

Contact Information

Contractor Jas General Construction; Lic. No.: 1026356-B 7858 PHLOX ST      DOWNEY, CA 90241
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/12/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 7/12/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 7/22/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/2/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/8/2022 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 9/8/2022 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 9/13/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 9/13/2022 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 9/21/2022 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Approved CRAIG VAUGHAN
Green Building Rough 9/21/2022 Approved CRAIG VAUGHAN
HVAC-Rough 9/21/2022 Approved CRAIG VAUGHAN
Insulation 9/29/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/29/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 10/4/2022 Approved CHARLES BOGHOSKHAN
Shower Pan 10/7/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 10/13/2022 Approved CHARLES BOGHOSKHAN
Final 2/14/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 2/14/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 2/14/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/3/2023 Approved CRAIG VAUGHAN
Final 3/3/2023 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 3/3/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 3/3/2023 Approved CRAIG VAUGHAN