1452-1454 W 37TH ST 90018

Certificate Information: 1452-1454 W 37TH ST 90018

Application / Permit
22012-10000-00012
Plan Check / Job No.
B22LA07580
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW DUPLEX WITH ATTACHED 2 CAR GARAGE (3-STORY)
Permit Issued
Issued on 6/16/2023
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 CARLOS MONTES
Corrections Issued 7/13/2022 CARLOS MONTES
Quality Review Completed 7/13/2022 GARO TELMI
Applicant returned to address corrections 2/6/2023 CARLOS MONTES
Plan Check Approved 5/18/2023 CARLOS MONTES
Issued 6/16/2023 APPLICANT
CofO in Progress 6/30/2025 SABAS ALONSO
Permit Finaled 7/8/2025 DEROLD HAUFF
CofO Issued 7/8/2025 DEROLD HAUFF
Permit Finaled 7/8/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/1/2023 JEANIE LAM
Sewer availability Cleared 2/8/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/14/2023 JEANIE LAM
Hydrant and Access approval Cleared 2/22/2023 JOHN CONNEALLY
Low Impact Development Cleared 4/27/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/1/2023 JEANIE LAM

Contact Information

Contractor Keystone D C S Inc; Lic. No.: 1013293-B       ,
Engineer Dong,, Truong Tan; Lic. No.: C75466 10692 SILVER CIRCLE      GARDEN GROVE, CA 92843

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2023 Partial Inspection SABAS ALONSO
Underground Mechanical 7/28/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 8/15/2023 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 8/15/2023 Corrections Issued SABAS ALONSO
METHANE-Barrier 8/15/2023 Approved SABAS ALONSO
METHANE-Subgrade 8/15/2023 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 8/18/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 8/31/2023 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/11/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 9/11/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval SABAS ALONSO
Sewer 1/8/2024 Approved SABAS ALONSO
HVAC-Rough 4/9/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 4/9/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 4/12/2024 Approved SABAS ALONSO
Deputy Wood Construction 4/30/2024 Conditional Approval SABAS ALONSO
METHANE-Rough 5/3/2024 Approved SABAS ALONSO
Pre-Inspection 5/3/2024 Partial Inspection SABAS ALONSO
ELECTRICAL-Rough 5/15/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 5/23/2024 Approved SABAS ALONSO
HVAC-Rough 5/23/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 6/12/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 6/12/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 6/12/2024 Corrections Issued CRAIG DAVIS
Verify Sprinkler Sign Off 6/12/2024 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Conditional Approval SABAS ALONSO
Rough-Elec/Plmb/HVAC 6/13/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 6/26/2024 Not Ready for Inspection SABAS ALONSO
Green Building Rough 6/26/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 6/26/2024 Approved SABAS ALONSO
Verify Sprinkler Sign Off 6/26/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 7/16/2024 Conditional Approval SABAS ALONSO
Green Building Rough 7/16/2024 Approved SABAS ALONSO
Insulation 8/6/2024 Corrections Issued ALEX COLIN
BUILDING-Rough-Frame 8/7/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 8/7/2024 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 8/13/2024 Corrections Issued ALEX COLIN
Insulation 8/19/2024 Approved SABAS ALONSO
Drywall Nailing 8/27/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 8/27/2024 Partial Approval SABAS ALONSO
Drywall Nailing 9/4/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 9/9/2024 Partial Approval SABAS ALONSO
Shower Pan 9/9/2024 Not Ready for Inspection SABAS ALONSO
Sewer 11/20/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 11/26/2024 Approved SABAS ALONSO
Service/Power Release 11/26/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 12/12/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 12/20/2024 Corrections Issued SABAS ALONSO
Gas Test 1/14/2025 Approved SABAS ALONSO
PLUMBING-Final 3/18/2025 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Final 3/25/2025 Approved SABAS ALONSO
PLUMBING-Final 3/25/2025 Approved SABAS ALONSO
HVAC-Final 4/7/2025 Approved SABAS ALONSO
Final 4/10/2025 Not Ready for Inspection SABAS ALONSO
Green Building Final 4/10/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 4/10/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 5/20/2025 Not Ready for Inspection SABAS ALONSO
Service/Power Release 5/22/2025 Not Ready for Inspection SABAS ALONSO
Final 6/26/2025 Conditional Approval SABAS ALONSO
Service/Power Release 6/26/2025 Approved SABAS ALONSO
Final 6/27/2025 OK to Issue CofO SABAS ALONSO
Service/Power Release 6/27/2025 Approved SABAS ALONSO