7001 W SANTA MONICA BLVD 90038
Certificate Information: 7001 W SANTA MONICA BLVD 90038
- Application / Permit
- 22010-40000-05460
- Plan Check / Job No.
- B22SP00060
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- PROPOSED RESTAURANT PER ZA-2022-3534-CU-WDI
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2022 | SINA KHOSRAVI |
| Corrections Issued | 11/23/2022 | SINA KHOSRAVI |
| Quality Review Completed | 12/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/6/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 1/5/2023 | APPLICANT |
| Applicant returned to address corrections | 2/10/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 3/7/2023 | SINA KHOSRAVI |
| Green Plans Picked Up | 3/7/2023 | APPLICANT |
| Applicant returned to address corrections | 4/3/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/23/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/10/2023 | SINA KHOSRAVI |
| Plan Check Approved | 7/10/2023 | SINA KHOSRAVI |
| Issued | 7/18/2023 | APPLICANT |
| Permit Finaled | 7/3/2025 | ADAM BURGESS |
| CofO Issued | 7/3/2025 | ADAM BURGESS |
| Permit Finaled | 7/3/2025 | ADAM BURGESS |
Permit Application Clearance Information
| Drainage to Storm Drain | Cleared | 1/13/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2023 | AMAAN MALIK |
| Driveway location | Cleared | 1/31/2023 | WESTON PRINGLE |
| Internal circulation | Cleared | 1/31/2023 | WESTON PRINGLE |
| "D" conditions | Cleared | 2/1/2023 | MIGUEL GAMBOA |
| ZI | Cleared | 2/1/2023 | MIGUEL GAMBOA |
| Work Adjacent to Public Way | Cleared | 2/9/2023 | JOSE RODRIGUEZ |
| Address approval | Cleared | 2/16/2023 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 2/16/2023 | RUEL COLE |
| Trees in Parkway | Cleared | 3/1/2023 | ADALBERTO VERA |
| Sewer availability | Cleared | 3/24/2023 | JEANETTE VONG |
| DAS Clearance | Cleared | 3/30/2023 | SINA KHOSRAVI |
| Green Code | Cleared | 3/30/2023 | AARON COSTA |
| Comm Cor/Mini-Mall | Cleared | 4/6/2023 | MIGUEL GAMBOA |
| Comm Cor/Mini-Mall | Cleared | 4/6/2023 | MIGUEL GAMBOA |
| Comm Cor/Mini-Mall | Cleared | 4/6/2023 | MIGUEL GAMBOA |
| ZA Case | Cleared | 4/6/2023 | MIGUEL GAMBOA |
| Food Service Establishment | Cleared | 4/27/2023 | PAWAN VERMA |
| Building over 36-ft | Cleared | 5/1/2023 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 5/1/2023 | CALOSHA APPROVED |
| Food establishment approval | Cleared | 5/1/2023 | LACDHS APPROVED |
| Fire Marshal Fire Life Safety | Cleared | 5/25/2023 | MENOA AGHAJANI |
| Highway dedication | Cleared | 6/14/2023 | TREVOR QUAN |
| Permit | Cleared | 6/14/2023 | TREVOR QUAN |
| Low Impact Development | Cleared | 6/16/2023 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 6/25/2023 | AHMED AMARRAGY |
Contact Information
| Architect | Baptista,, Jay P; Lic. No.: C27684 | STANTEC ARCHITECTURE INC 3133 W FRYE ROAD #300 CHANDLER, AZ 85226 |
| Contractor | Pcl Construction Services Inc; Lic. No.: 474555-B | 655 N CENTRAL AVENUE STE 1600 GLENDALE, CA 91203 |
| Engineer | Rice,, Joseph Henry; Lic. No.: S6728 | PO BOX 227 MORRO BAY, CA 93443 |
Inspector Information
| EDWIN GREGORYONA, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/5/2023 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 9/15/2023 | Partial Inspection | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/20/2023 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 9/20/2023 | Partial Approval | EDWIN GREGORYONA |
| Pre-Inspection | 9/20/2023 | Approved | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/21/2023 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 9/21/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/26/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 9/27/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/28/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/5/2023 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 10/5/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 10/7/2023 | Approved | TED RIES |
| Deputy Reinf. Concrete | 10/10/2023 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 10/10/2023 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/12/2023 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 10/12/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 10/16/2023 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 10/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 10/18/2023 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 10/18/2023 | Partial Approval | EDWIN GREGORYONA |
| Special/Order Compliance | 10/31/2023 | Approved | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 11/21/2023 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 11/21/2023 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 11/21/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/6/2023 | Partial Approval | EDWIN GREGORYONA |
| Pre-Inspection | 12/8/2023 | Approved | EDWIN GREGORYONA |
| Structural Steel Frame | 12/8/2023 | Partial Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 12/29/2023 | Partial Approval | EDWIN GREGORYONA |
| Structural Steel Frame | 12/29/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/2/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 1/8/2024 | Partial Approval | EDWIN GREGORYONA |
| Pre-Inspection | 1/8/2024 | Approved | EDWIN GREGORYONA |
| Deputy Grading | 1/24/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/24/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 1/25/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/29/2024 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 1/29/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 1/30/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 1/31/2024 | Not Ready for Inspection | EDWIN GREGORYONA |
| Drywall Nailing | 2/1/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 2/2/2024 | Partial Inspection | EDWIN GREGORYONA |
| Light Gage Steel Frame | 2/8/2024 | Partial Approval | EDWIN GREGORYONA |
| Structural Steel Frame | 2/8/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 2/9/2024 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 2/15/2024 | Partial Approval | EDWIN GREGORYONA |
| Pre-Inspection | 2/16/2024 | Approved | EDWIN GREGORYONA |
| Structural Steel Frame | 2/16/2024 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 2/22/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 2/28/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 3/7/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 3/12/2024 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 3/12/2024 | Partial Inspection | EDWIN GREGORYONA |
| Drywall Nailing | 4/4/2024 | Partial Approval | EDWIN GREGORYONA |
| Special/Order Compliance | 4/11/2024 | Approved | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 4/16/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 4/17/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Drywall Nailing | 4/19/2024 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 4/22/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 4/23/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 4/30/2024 | Not Ready for Inspection | EDWIN GREGORYONA |
| Drywall Nailing | 5/2/2024 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 5/15/2024 | Partial Approval | EDWIN GREGORYONA |
| T-Bar Ceiling | 5/15/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 5/23/2024 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 7/3/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 7/8/2024 | Partial Inspection | EDWIN GREGORYONA |
| T-Bar Ceiling | 7/17/2024 | Partial Approval | EDWIN GREGORYONA |
| T-Bar Ceiling | 7/19/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/15/2024 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 8/15/2024 | Partial Approval | EDWIN GREGORYONA |
| T-Bar Ceiling | 9/13/2024 | Not Ready for Inspection | DAVID BURKHEAD |
| Special/Order Compliance | 9/25/2024 | Partial Approval | MARTIN TAVITIAN |
| Special/Order Compliance | 11/21/2024 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 12/18/2024 | Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 2/3/2025 | Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 2/5/2025 | Approved | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 2/27/2025 | Partial Approval | EDWIN GREGORYONA |
| Special/Order Compliance | 3/13/2025 | Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 6/3/2025 | Approved | EDWIN GREGORYONA |
| Final | 6/24/2025 | Conditional Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/24/2025 | Approved | EDWIN GREGORYONA |
| Green Building Final | 6/24/2025 | Approved | EDWIN GREGORYONA |
| Green Building Rough | 6/24/2025 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 6/24/2025 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 6/24/2025 | Approved | EDWIN GREGORYONA |
| Wood Frame | 6/24/2025 | Approved | EDWIN GREGORYONA |