1623 S GENESEE AVE 90019

Certificate Information: 1623 S GENESEE AVE 90019

Application / Permit
22010-40000-05393
Plan Check / Job No.
B22SP00053
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(n) detached 1-story 2-car garage U Occupancy 2 of 2
Permit Issued
Issued on 12/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 KELVIN CHUONG
Corrections Issued 2/14/2023 KELVIN CHUONG
Quality Review Completed 2/15/2023 RODOLFO ARIAS
Applicant returned to address corrections 9/12/2023 KELVIN CHUONG
Applicant returned to address corrections 9/26/2023 KELVIN CHUONG
Applicant returned to address corrections 10/5/2023 KELVIN CHUONG
Applicant returned to address corrections 10/26/2023 KELVIN CHUONG
Applicant returned to address corrections 11/29/2023 KELVIN CHUONG
Applicant returned to address corrections 12/4/2023 KELVIN CHUONG
Applicant returned to address corrections 12/6/2023 KELVIN CHUONG
Plan Check Approved 12/19/2023 KELVIN CHUONG
Issued 12/21/2023 APPLICANT
CofO in Progress 12/9/2024 ENRIQUE MIRELES
Permit Finaled 12/12/2024 DEROLD HAUFF
CofO Issued 12/12/2024 DEROLD HAUFF
Permit Finaled 12/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Stormwater Pollution Mitigatn Cleared 9/25/2023 MELINEH AGHAKHABIAN
Eng Process Fee Ord 176,300 Cleared 10/6/2023 JEANIE LAM
Hydrant and Access approval Cleared 10/6/2023 KURT CORRAL
Permit Cleared 10/6/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 10/6/2023 JEANIE LAM
Sewer availability Cleared 10/6/2023 JEANIE LAM
Trees in Parkway Cleared 12/14/2023 ADALBERTO VERA

Contact Information

Contractor Don Construction; Lic. No.: 840108-B 28063 MEMORY LN      VALENCIA, CA 91354

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/16/2024 Approved RONNIE MINDANAO
Footing/Foundation/Slab 1/16/2024 Approved RONNIE MINDANAO
METHANE-Barrier 1/16/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 1/16/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 2/16/2024 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 3/18/2024 No Access for Inspection STUART CHAPMAN
Green Building Rough 3/18/2024 No Access for Inspection STUART CHAPMAN
Interior/Exterior Lathing 3/18/2024 No Access for Inspection STUART CHAPMAN
METHANE-Rough 3/18/2024 No Access for Inspection STUART CHAPMAN
Wood Frame 3/18/2024 No Access for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 3/19/2024 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 3/19/2024 Approved STUART CHAPMAN
Green Building Rough 3/19/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/19/2024 Partial Approval STUART CHAPMAN
METHANE-Rough 3/19/2024 Approved STUART CHAPMAN
Pre-Inspection 3/19/2024 Partial Inspection STUART CHAPMAN
Drywall Nailing 4/2/2024 Approved RICHARD DOCKUS
Service/Power Release 5/9/2024 Corrections Issued RICHARD DOCKUS
Service/Power Release 6/24/2024 Corrections Issued ENRIQUE MIRELES
Service/Power Release 7/2/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 7/17/2024 Approved ARTHUR NEGRETE
Service/Power Release 7/17/2024 Corrections Issued ARTHUR NEGRETE
BUILDING-Rough-Frame 11/21/2024 Approved ARTHUR NEGRETE
Final 11/21/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 11/21/2024 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 11/21/2024 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 11/21/2024 Approved ARTHUR NEGRETE
Final 12/2/2024 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 12/2/2024 Approved ENRIQUE MIRELES
Service/Power Release 12/2/2024 Approved ENRIQUE MIRELES