1623 S GENESEE AVE 90019

Certificate Information: 1623 S GENESEE AVE 90019

Application / Permit
22010-40000-05392
Plan Check / Job No.
B22SP00053
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 2- story SFD R3 occupancy NFPA 13D sprinklered throughout 1 of 2
Permit Issued
Issued on 12/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2022 APPLICANT
Assigned to Plan Check Engineer 11/22/2022 KELVIN CHUONG
Corrections Issued 2/14/2023 KELVIN CHUONG
Quality Review Completed 2/15/2023 RODOLFO ARIAS
Applicant returned to address corrections 9/12/2023 KELVIN CHUONG
Applicant returned to address corrections 9/26/2023 KELVIN CHUONG
Applicant returned to address corrections 10/5/2023 KELVIN CHUONG
Applicant returned to address corrections 10/26/2023 KELVIN CHUONG
Applicant returned to address corrections 11/29/2023 KELVIN CHUONG
Applicant returned to address corrections 12/4/2023 KELVIN CHUONG
Applicant returned to address corrections 12/6/2023 KELVIN CHUONG
Plan Check Approved 12/19/2023 KELVIN CHUONG
Issued 12/21/2023 APPLICANT
CofO in Progress 12/9/2024 ENRIQUE MIRELES
Permit Finaled 12/12/2024 DEROLD HAUFF
CofO Issued 12/12/2024 DEROLD HAUFF
Permit Finaled 12/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Stormwater Pollution Mitigatn Cleared 9/25/2023 MELINEH AGHAKHABIAN
Eng Process Fee Ord 176,300 Cleared 9/29/2023 JESSICA OPINION
Permit Cleared 9/29/2023 JESSICA OPINION
Sewer availability Cleared 9/29/2023 JESSICA OPINION
Roof/Waste drainage to street Cleared 10/4/2023 DAVID VO
Hydrant and Access approval Cleared 10/6/2023 KURT CORRAL

Contact Information

Contractor Don Construction; Lic. No.: 840108-B 28063 MEMORY LN      VALENCIA, CA 91354

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/27/2023 Partial Approval SCOTT FINNILA
METHANE-Subgrade 12/27/2023 Partial Approval SCOTT FINNILA
PLUMBING-Rough 12/27/2023 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 1/4/2024 Partial Approval RONNIE MINDANAO
METHANE-Barrier 1/8/2024 Approved RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 1/16/2024 Approved RONNIE MINDANAO
Footing/Foundation/Slab 1/16/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 1/16/2024 Approved RONNIE MINDANAO
Deputy Reinf. Concrete 1/17/2024 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Partial Approval BRENDAN MORELLI
Wood Frame 1/29/2024 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 2/16/2024 Partial Approval STUART CHAPMAN
Deputy Wood Construction 2/16/2024 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval STUART CHAPMAN
Green Building Rough 2/16/2024 No Access for Inspection STUART CHAPMAN
METHANE-Rough 2/16/2024 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 2/16/2024 Not Ready for Inspection STUART CHAPMAN
Wood Frame 2/16/2024 Partial Approval STUART CHAPMAN
Wood Frame 3/1/2024 Partial Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 3/18/2024 No Access for Inspection STUART CHAPMAN
Green Building Rough 3/18/2024 No Access for Inspection STUART CHAPMAN
Interior/Exterior Lathing 3/18/2024 No Access for Inspection STUART CHAPMAN
METHANE-Rough 3/18/2024 No Access for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 3/18/2024 No Access for Inspection STUART CHAPMAN
Sewer 3/18/2024 Not Ready for Inspection STUART CHAPMAN
Shower Pan 3/18/2024 No Access for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 3/18/2024 No Access for Inspection STUART CHAPMAN
ELECTRICAL-Final 3/19/2024 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 3/19/2024 Approved STUART CHAPMAN
Gas Test 3/19/2024 Partial Inspection STUART CHAPMAN
Green Building Rough 3/19/2024 Approved STUART CHAPMAN
HVAC-Rough 3/19/2024 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 3/19/2024 Partial Approval STUART CHAPMAN
PLUMBING-Rough 3/19/2024 Approved STUART CHAPMAN
Pre-Inspection 3/19/2024 Partial Inspection STUART CHAPMAN
Sewer 3/19/2024 Approved STUART CHAPMAN
Shower Pan 3/19/2024 Approved STUART CHAPMAN
HVAC-Rough 3/26/2024 Approved BRENDAN MORELLI
Insulation 3/26/2024 Approved BRENDAN MORELLI
Drywall Nailing 4/2/2024 Approved RICHARD DOCKUS
Interior/Exterior Lathing 4/2/2024 Partial Approval RICHARD DOCKUS
Service/Power Release 4/8/2024 Not Ready for Inspection RICHARD DOCKUS
Service/Power Release 5/9/2024 Corrections Issued RICHARD DOCKUS
Service/Power Release 6/24/2024 Corrections Issued ENRIQUE MIRELES
Service/Power Release 7/2/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 7/17/2024 Approved ARTHUR NEGRETE
Service/Power Release 7/17/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 11/21/2024 Partial Approval ARTHUR NEGRETE
Final 11/21/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 11/21/2024 Not Ready for Inspection ARTHUR NEGRETE
METHANE-Final 11/21/2024 Corrections Issued ARTHUR NEGRETE
METHANE-Rough 11/21/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 11/21/2024 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 11/21/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 12/2/2024 Approved ENRIQUE MIRELES
Final 12/2/2024 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 12/2/2024 Approved ENRIQUE MIRELES
METHANE-Final 12/2/2024 Approved ENRIQUE MIRELES
METHANE-Rough 12/2/2024 Approved ENRIQUE MIRELES