876 N NORMAN PL 90049

Certificate Information: 876 N NORMAN PL 90049

Application / Permit
22010-30001-00648
Plan Check / Job No.
B22WL04325
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental permit to # 22010-30000-00648 to reduce size of the building, update structural inventory and checklist items
Permit Issued
Issued on 5/8/2023
Issuing Office
Current Status
Permit Finaled on 7/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 REZA HAGHIGHAT
Corrections Issued 12/6/2022 REZA HAGHIGHAT
Quality Review Completed 12/8/2022 CHIHARU SUZUKI
Building Plans Picked Up 12/12/2022 APPLICANT
Applicant returned to address corrections 2/22/2023 YASHAR EMAMI
Plan Check Approved 4/26/2023 REZA HAGHIGHAT
Issued 5/8/2023 APPLICANT
Permit Finaled 7/16/2024 CARLOS MATAMOROS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/27/2022 JENSON LEE
Watercourse Cleared 12/28/2022 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 2/27/2023 ANTHONY MAINEZ

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/6/2023 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 7/6/2023 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 8/3/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 8/3/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 8/22/2023 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 8/22/2023 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 8/29/2023 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 8/29/2023 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/6/2023 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 9/6/2023 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 9/7/2023 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Conditional Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 11/3/2023 Approved CARLOS MATAMOROS
HVAC-Rough 11/7/2023 Approved CARLOS MATAMOROS
Shower Pan 11/27/2023 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 1/4/2024 Not Ready for Inspection CARLOS MATAMOROS
FLOOD-Proofing Certificate 1/4/2024 Approved CARLOS MATAMOROS
Green Building Rough 1/4/2024 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 1/4/2024 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 1/5/2024 No Access for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 1/9/2024 Approved CARLOS MATAMOROS
Green Building Rough 1/9/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 1/9/2024 Approved CARLOS MATAMOROS
Insulation 1/12/2024 Approved CARLOS MATAMOROS
Insulation 1/16/2024 Approved CARLOS MATAMOROS
Drywall Nailing 1/24/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 1/31/2024 Approved CARLOS MATAMOROS
Underground Mechanical 1/31/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/12/2024 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 3/28/2024 Partial Approval EVAN COOPER
Final 7/16/2024 Permit Finaled CARLOS MATAMOROS
Green Building Final 7/16/2024 Approved CARLOS MATAMOROS
Green Building Rough 7/16/2024 Approved CARLOS MATAMOROS
Sewer 7/16/2024 Corrections Issued CARLOS MATAMOROS