1161 N RAVOLI DR 90272

Certificate Information: 1161 N RAVOLI DR 90272

Application / Permit
22010-30000-06490
Plan Check / Job No.
B22WL04650
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new two story S.F.D. over basement with attached 2-car garage . *** 1 of 3 *** see comments **
Permit Issued
Issued on 3/6/2024
Issuing Office
West Los Angeles
Current Status
Issued on 3/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 1/11/2023 KAVIAN REFAHI
Corrections Issued 1/16/2023 KAVIAN REFAHI
Quality Review Completed 1/18/2023 CHIHARU SUZUKI
Building Plans Picked Up 1/19/2023 APPLICANT
Applicant returned to address corrections 7/14/2023 KAVIAN REFAHI
Applicant returned to address corrections 9/6/2023 KAVIAN REFAHI
Plan Check Approved 2/28/2024 KAVIAN REFAHI
Issued 3/6/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/23/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/23/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/23/2023 ANTHONY MAINEZ
Permit Cleared 2/23/2023 ANTHONY MAINEZ
Miscellaneous Cleared 4/13/2023 SAUL GARCIA
BHO/Hillside ordinance Cleared 4/23/2023 AHMED AMARRAGY
BHO/Hillside ordinance Cleared 4/23/2023 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 5/22/2023 JASON NG
Sewer availability Cleared 5/22/2023 JASON NG
GPI Written Notices Cleared 6/16/2023 KAVIAN REFAHI
Grading Pre-Inspection Cleared 6/16/2023 KAVIAN REFAHI
Trees in Parkway Cleared 7/20/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 9/26/2023 LAVEON RIDER
Low Impact Development Cleared 10/19/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/22/2023 AHMED AMARRAGY
Disturb/Remove Protected Trees Cleared 2/6/2024 ADALBERTO VERA
Excavation more than 5-ft deep Cleared 2/21/2024 CALOSHA APPROVED

Contact Information

Architect Schenk,, Monique Doris; Lic. No.: C22699 4156 CRISP CANYON RD      SHERMAN OAKS, CA 91403
Contractor Core Development Group Inc; Lic. No.: 845288-B 1112 MONTANA AVE #204      SANTA MONICA, CA 90403
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Barajas,, Alejandro Leon; Lic. No.: S4773 565 PEARL ST STE 209      LA JOLLA, CA 92037
Engineer Silverman,, David; Lic. No.: C58650 22837 VENTURA BLVD SUITE 100      WOODLAND HILLS, CA 91364
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Landscape Architect Arquieta,, Perla; Lic. No.: LA4701 205 RUTH AVE      VENICE, CA 90291

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2024 Partial Inspection KEVIN SARGSYAN
Deputy Reinf. Concrete 7/24/2024 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/25/2024 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 7/25/2024 Partial Approval KEVIN SARGSYAN
Underground Mechanical 7/25/2024 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/12/2024 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/19/2024 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 8/20/2024 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 8/29/2024 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 9/3/2024 Partial Approval HERBERT GIRON
Deputy Wood Construction 9/25/2024 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 10/7/2024 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 10/17/2024 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 10/17/2024 Partial Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 10/23/2024 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 10/23/2024 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 10/24/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 12/9/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 12/18/2024 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Corrections Issued KEVIN SARGSYAN
Sewer 2/11/2025 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Partial Approval EVAN COOPER
PLUMBING-Rough 2/21/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Corrections Issued HERBERT GIRON
Underground Mechanical 6/25/2025 Corrections Issued HERBERT GIRON
Underground Mechanical 6/26/2025 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 6/30/2025 Corrections Issued HERBERT GIRON
HVAC-Rough 7/8/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Approved HERBERT GIRON
HVAC-Rough 7/15/2025 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 7/15/2025 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 7/29/2025 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 7/30/2025 Corrections Issued STEPHANIE SWANSON
Green Building Rough 7/30/2025 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 7/30/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 8/22/2025 Approved STEPHANIE SWANSON
Insulation 8/22/2025 Partial Approval STEPHANIE SWANSON
Insulation 8/26/2025 Approved MEL KHACHATOURIAN
Drywall Nailing 9/3/2025 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Approved TEMISTOCLES CAAL
Shower Pan 9/9/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 9/15/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 9/23/2025 Approved TEMISTOCLES CAAL