5216 N AUCKLAND AVE 91601
Certificate Information: 5216 N AUCKLAND AVE 91601
- Application / Permit
- 22010-30000-06236
- Plan Check / Job No.
- B22WL04569
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 3-story S.F.D. in middle *** 2 of 3 ***
- Permit Issued
- Issued on 3/24/2023
- Issuing Office
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2023 | KAVIAN REFAHI |
| Corrections Issued | 1/15/2023 | KAVIAN REFAHI |
| Quality Review Completed | 1/18/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 1/26/2023 | APPLICANT |
| Plan Check Approved | 3/1/2023 | KAVIAN REFAHI |
| Issued | 3/24/2023 | APPLICANT |
| CofO in Progress | 4/22/2025 | RYAN SALAZAR |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
| CofO Issued | 4/24/2025 | RUBEN SALAS |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2023 | DAGOVERTO GUERRERO |
| Highway dedication | Cleared | 1/12/2023 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 1/12/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/13/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2023 | DAGOVERTO GUERRERO |
| SB8 RUD | Cleared | 2/3/2023 | KENNETH LE |
| Sewer availability | Cleared | 2/3/2023 | DAGOVERTO GUERRERO |
| CPC | Cleared | 2/9/2023 | MAXFIELD VERMY |
| Frnt yard landscape/Water mgmt | Cleared | 2/9/2023 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 2/9/2023 | KURT CORRAL |
Contact Information
| Architect | Dehghan,, Hamid; Lic. No.: C35150 | 2355 WESTWOOD BLVD # 900 LOS ANGELES, CA 90064 |
| Contractor | R & M Real Estate Investments And Renovators Inc; Lic. No.: 1075969-B | 10910 LONG BEACH BLVD STE 103 LYNWOOD, CA 902622683 |
| Engineer | Masud,, Fahad M; Lic. No.: C92662 | 2415 EATON COURT ORANGE, CA 92867 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| HVAC-Final | 4/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 4/11/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 4/14/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 5/1/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 5/5/2023 | Approved | JOHN HAYES |
| Deputy Wood Construction | 5/24/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | JOHN HAYES |
| Deputy Wood Construction | 6/16/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/14/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 11/17/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Rough | 11/17/2023 | Not Ready for Inspection | ROBERT GOLD |
| Verify Sprinkler Sign Off | 11/17/2023 | Not Ready for Inspection | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 12/12/2023 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 12/12/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/15/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 12/15/2023 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 12/15/2023 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 1/25/2024 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 1/30/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 1/30/2024 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/30/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 1/30/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/30/2024 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 1/30/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 2/6/2024 | Approved | JOHN HAYES |
| HVAC-Rough | 2/6/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/6/2024 | Partial Approval | JOHN HAYES |
| Pre-Inspection | 2/15/2024 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/23/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 2/23/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/23/2024 | Partial Approval | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 2/23/2024 | Approved | RYAN SALAZAR |
| Insulation | 3/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/6/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 4/10/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/6/2024 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 5/8/2024 | Partial Approval | JACK KARGODORIAN |
| Sewer | 9/5/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 2/7/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 2/7/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 2/21/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/21/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 2/27/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Final | 2/27/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Final | 2/27/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 3/6/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Final | 3/6/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 3/19/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/19/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 3/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 3/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/19/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 3/27/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/27/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 4/7/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 4/14/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 4/14/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 4/21/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 4/21/2025 | Approved | RYAN SALAZAR |