5465 S 4TH AVE 90043
Certificate Information: 5465 S 4TH AVE 90043
- Application / Permit
- 22010-30000-06203
- Plan Check / Job No.
- B22WL04542
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Construct New ADU over New Garage per Ordianance (LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 2/7/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 2/3/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 2/7/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/10/2023 | APPLICANT |
| Applicant returned to address corrections | 11/9/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 1/31/2024 | HOOMAN HAJIZADEH |
| Issued | 2/7/2024 | APPLICANT |
| CofO in Progress | 8/16/2025 | LUIS CASTRO |
| Permit Finaled | 8/16/2025 | DEROLD HAUFF |
| CofO Issued | 8/16/2025 | DEROLD HAUFF |
| Permit Finaled | 8/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 11/21/2023 | CHRISTINA BRACO |
| Stormwater Pollution Mitigatn | Cleared | 1/19/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 1/20/2024 | ADRIAN SANCHEZ |
| Low Impact Development (LID) | Cleared | 1/22/2024 | LUIS LUVANO |
| Construction near power lines | Cleared | 1/24/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lotfi,, Fariborz F; Lic. No.: C49359 | 1328 DUENDE LANE PACIFIC PALISADES, CA 90272 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 5/20/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/20/2024 | Partial Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 6/21/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/14/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Wood Construction | 9/3/2024 | Conditional Approval | ANTHONY EGSON |
| PLUMBING-Rough | 9/3/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/20/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/20/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 9/20/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 9/20/2024 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 9/20/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/2/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 10/2/2024 | Approved | ANTHONY EGSON |
| Wood Frame | 10/2/2024 | Corrections Issued | ANTHONY EGSON |
| Insulation | 10/22/2024 | Approved | JOSH MEISTER |
| Sewer | 10/22/2024 | Approved | JOSH MEISTER |
| Underground Mechanical | 10/22/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/30/2024 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 11/4/2024 | Partial Inspection | JOSH MEISTER |
| Drywall Nailing | 11/5/2024 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 11/5/2024 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 11/7/2024 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 11/18/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 5/9/2025 | Approved | LUIS CASTRO |
| Final | 5/9/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 5/9/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 8/8/2025 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 8/15/2025 | Approved | LUIS CASTRO |
| Final | 8/15/2025 | OK to Issue CofO | LUIS CASTRO |
| Footing/Foundation/Slab | 8/15/2025 | Approved | LUIS CASTRO |
| Green Building Final | 8/15/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 8/15/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Approved | LUIS CASTRO |
| Service/Power Release | 8/15/2025 | Approved | LUIS CASTRO |
| Smoke Detectors | 8/15/2025 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 8/15/2025 | Approved | LUIS CASTRO |