10351 S HICKORY ST 90002

Certificate Information: 10351 S HICKORY ST 90002

Application / Permit
22010-30000-06178
Plan Check / Job No.
B22WL04530
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story S.F.D. in the front of the lot. *** 1 of 3 ***
Permit Issued
Issued on 1/26/2024
Issuing Office
Metro
Current Status
Issued on 1/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/14/2022 APPLICANT
Assigned to Plan Check Engineer 12/22/2022 JAHANSHAH POURHASSAN
Corrections Issued 12/27/2022 JAHANSHAH POURHASSAN
Quality Review Completed 1/5/2023 CHIHARU SUZUKI
Building Plans Picked Up 1/6/2023 APPLICANT
Applicant returned to address corrections 2/8/2023 JAHANSHAH POURHASSAN
Plan Check Approved 3/1/2023 JAHANSHAH POURHASSAN
Issued 1/26/2024 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 1/17/2023 ROGELIO CORTES
Address approval Cleared 1/24/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 1/24/2023 AMAAN MALIK
Hydrant and Access approval Cleared 1/27/2023 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 2/3/2023 AMAAN MALIK
Sewer availability Cleared 2/3/2023 AMAAN MALIK

Contact Information

Architect Hamid, Dehghan; Lic. No.: C35150       ,
Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2024 Partial Approval BEN MOLSTAD
Underground Mechanical 3/15/2024 Approved BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 4/3/2024 Not Ready for Inspection BEN MOLSTAD
Footing/Foundation/Slab 4/3/2024 Not Ready for Inspection BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 4/8/2024 Approved BEN MOLSTAD
Special/Order Compliance 4/8/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Partial Approval BEN MOLSTAD
Deputy Wood Construction 8/8/2024 Conditional Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 8/16/2024 Not Ready for Inspection BEN MOLSTAD
Sewer 8/16/2024 Partial Approval BEN MOLSTAD
HVAC-Rough 10/17/2024 Corrections Issued BARRY HACHE
PLUMBING-Rough 10/17/2024 Corrections Issued BARRY HACHE
HVAC-Rough 10/24/2024 Approved ANTHONY EGSON
PLUMBING-Rough 10/24/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 10/29/2024 Approved ANTHONY EGSON
PLUMBING-Rough 10/29/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 1/8/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 3/28/2025 Approved JOSEPH MCGARRY