166 N ASHDALE PL 90049
Certificate Information: 166 N ASHDALE PL 90049
- Application / Permit
- 22010-30000-06137
- Plan Check / Job No.
- B22WL04523
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story S.F.R. w/ 2-car garage attached by covered carprort, two story basement. *** 1 of 5 ***
- Permit Issued
- Issued on 9/20/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 9/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2022 | KAVIAN REFAHI |
| Corrections Issued | 1/10/2023 | KAVIAN REFAHI |
| Quality Review Completed | 1/12/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 1/13/2023 | APPLICANT |
| Applicant returned to address corrections | 2/13/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/19/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/31/2023 | KAVIAN REFAHI |
| Plan Check Approved | 9/20/2023 | KAVIAN REFAHI |
| Issued | 9/20/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2023 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 1/25/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 1/25/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 1/25/2023 | JASON NG |
| Permit | Cleared | 1/25/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2023 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/21/2023 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 2/21/2023 | ADALBERTO VERA |
| BHO/Hillside ordinance | Cleared | 4/13/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 4/13/2023 | JASON NG |
| Hydrant and Access approval | Cleared | 4/20/2023 | RUEL COLE |
| Low Impact Development | Cleared | 5/26/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/19/2023 | AHMED AMARRAGY |
| Excavation more than 5-ft deep | Cleared | 7/31/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 7/31/2023 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 7/31/2023 | KAVIAN REFAHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/17/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 4/23/2024 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/23/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 5/23/2024 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/23/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 6/7/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/10/2024 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 6/10/2024 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/14/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 6/17/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/20/2024 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/20/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 6/21/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/27/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 7/5/2024 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 7/22/2024 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/22/2024 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/1/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/14/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 8/20/2024 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/9/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 9/13/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 9/16/2024 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/16/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/16/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 9/18/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 9/19/2024 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/26/2024 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 9/26/2024 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 9/27/2024 | Conditional Approval | MICHAEL PELHAM |
| Special/Order Compliance | 10/15/2024 | Approved | CARLOS MATAMOROS |
| Sewer | 10/18/2024 | Corrections Issued | CARLOS MATAMOROS |
| Sewer | 10/22/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 10/30/2024 | Partial Approval | CHRISTOPHER WILSON |
| Sewer | 11/1/2024 | Corrections Issued | CARLOS MATAMOROS |
| Sewer | 11/4/2024 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 11/4/2024 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/8/2024 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/14/2024 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/15/2024 | Partial Approval | CARLOS MATAMOROS |
| Sewer | 11/15/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 11/18/2024 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/20/2024 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 11/25/2024 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/6/2024 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 12/9/2024 | Conditional Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 12/13/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/13/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/3/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 2/4/2025 | Partial Approval | CARLOS MATAMOROS |
| Structural Steel Frame | 2/21/2025 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 2/27/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/3/2025 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 4/14/2025 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/2/2025 | Partial Approval | BOBBY KEY |
| Reinforced Concrete Frame | 7/2/2025 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 7/9/2025 | Conditional Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/19/2025 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 10/28/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 10/28/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/28/2025 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 12/22/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 12/22/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/22/2025 | Corrections Issued | CARLOS MATAMOROS |
| Special/Order Compliance | 12/22/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/23/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/31/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/7/2026 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 1/8/2026 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2026 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 1/14/2026 | Partial Approval | EVAN COOPER |
| Insulation | 2/4/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/6/2026 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 3/12/2026 | Approved | EVAN COOPER |
| Shower Pan | 4/13/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/15/2026 | Approved | EVAN COOPER |
| Underground Mechanical | 4/28/2026 | Corrections Issued | CHRISTOPHER WILSON |