3540-3542 S BUTLER AVE 90066
Certificate Information: 3540-3542 S BUTLER AVE 90066
- Application / Permit
- 22010-30000-05992
- Plan Check / Job No.
- B22WL04467
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD w./ att. 2-car garage and att. ADU per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 6/10/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 6/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2023 | REZA HAGHIGHAT |
| Corrections Issued | 1/13/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 1/18/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 1/19/2023 | APPLICANT |
| Plan Check Approved | 6/25/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 2/21/2025 | REZA HAGHIGHAT |
| Issued | 6/10/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2023 | JASON NG |
| Permit | Cleared | 7/3/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2023 | JASON NG |
| Sewer availability | Cleared | 8/11/2023 | JASON NG |
| Hydrant and Access approval | Cleared | 8/18/2023 | LAVEON RIDER |
| Trees in Parkway | Cleared | 10/26/2023 | ADALBERTO VERA |
| Specific Plan | Cleared | 11/9/2023 | JOSHUA JONES |
| Low Impact Development | Cleared | 12/6/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 12/27/2023 | AHMED AMARRAGY |
| GPI Written Notices | Cleared | 1/4/2024 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 1/4/2024 | REZA HAGHIGHAT |
| SB8 RUD | Cleared | 4/26/2024 | BLAKE BOULIGNY |
| Construction near power lines | Cleared | 5/28/2024 | WALTER RAMIREZ |
| Miscellaneous | Cleared | 6/24/2024 | NOAH MCCOY |
Contact Information
| Architect | Winters,, Patrick Charles; Lic. No.: C22032 | 11410 BIONA DRIVE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Varela,, Benjamin; Lic. No.: S5714 | 6007 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Gas Test | 8/6/2026 |
| ELECTRICAL-Final | 8/6/2026 |
| PLUMBING-Final | 8/6/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/24/2025 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 7/24/2025 | Partial Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 8/1/2025 | Corrections Issued | KIRK SANDERS |
| Pre-Inspection | 8/1/2025 | Partial Inspection | KIRK SANDERS |
| Underground Mechanical | 8/1/2025 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 8/11/2025 | Approved | BOBBY KEY |
| Pre-Inspection | 8/11/2025 | Partial Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 9/12/2025 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 9/12/2025 | Not Ready for Inspection | KIRK SANDERS |
| Pre-Inspection | 9/12/2025 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 9/12/2025 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/26/2025 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 12/26/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 12/26/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/6/2026 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 1/6/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 1/6/2026 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 1/6/2026 | Approved | KIRK SANDERS |
| Pre-Inspection | 1/6/2026 | Not Ready for Inspection | KIRK SANDERS |
| Structural Steel Frame | 1/6/2026 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 1/6/2026 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/22/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 1/22/2026 | Approved | MICHAEL ALLEN |
| Green Building Rough | 1/22/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 1/22/2026 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 1/22/2026 | Approved | MICHAEL ALLEN |
| Shower Pan | 1/22/2026 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 1/22/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 1/29/2026 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/6/2026 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 2/12/2026 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 3/2/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 8/4/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 8/4/2026 | Corrections Issued | KIRK SANDERS |
| Pre-Inspection | 8/4/2026 | Partial Inspection | KIRK SANDERS |