262 N HOMEWOOD ROAD 90049

Certificate Information: 262 N HOMEWOOD ROAD 90049

Application / Permit
22010-30000-05857
Plan Check / Job No.
B22WL04156
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/8/2024
Issuing Office
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2022 APPLICANT
Assigned to Plan Check Engineer 11/23/2022 KAVIAN REFAHI
Corrections Issued 12/5/2022 KAVIAN REFAHI
Quality Review Completed 12/8/2022 CHIHARU SUZUKI
Building Plans Picked Up 12/12/2022 APPLICANT
Applicant returned to address corrections 3/6/2023 KAVIAN REFAHI
Applicant returned to address corrections 4/11/2023 KAVIAN REFAHI
Applicant returned to address corrections 4/12/2023 KAVIAN REFAHI
Applicant returned to address corrections 12/4/2023 KAVIAN REFAHI
Applicant returned to address corrections 1/17/2024 KAVIAN REFAHI
Applicant returned to address corrections 1/29/2024 KAVIAN REFAHI
Plan Check Approved 2/1/2024 KAVIAN REFAHI
Issued 2/8/2024 APPLICANT
CofO in Progress 5/4/2026 KEVIN SARGSYAN
Permit Finaled 5/11/2026 RICHARD STEINBACH
CofO Issued 5/11/2026 RICHARD STEINBACH
Permit Finaled 5/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/10/2023 JENSON LEE
Watercourse Cleared 1/11/2023 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 1/12/2023 JENSON LEE
Sewer availability Cleared 1/12/2023 JENSON LEE
GPI Written Notices Cleared 3/28/2023 KAVIAN REFAHI
Grading Pre-Inspection Cleared 3/28/2023 KAVIAN REFAHI
Low Impact Development Cleared 4/25/2023 LUIS LUVANO
Construction near power lines Cleared 5/3/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 5/18/2023 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 7/20/2023 KURT CORRAL

Contact Information

Contractor Fronen Construction Inc; Lic. No.: 1053555-B 12400 VENTURA BLVD #336      STUDIO CITY, CA 91604
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Geologist Feffer,, Joshua R; Lic. No.: GEO6861 12253 GORHAM AVENUE      LOS ANGELES, CA 90049

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/16/2024 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 9/9/2024 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 9/10/2024 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 11/8/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 1/3/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 1/3/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/3/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 1/7/2025 Approved KEVIN SARGSYAN
HVAC-Rough 1/7/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 1/29/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 1/29/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/29/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 2/3/2025 Conditional Approval JESUS RODRIGUEZ
Green Building Rough 2/3/2025 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 2/3/2025 Approved JESUS RODRIGUEZ
Insulation 2/12/2025 Approved KEVIN SARGSYAN
Shower Pan 2/12/2025 Approved KEVIN SARGSYAN
Drywall Nailing 2/21/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/21/2025 Approved KEVIN SARGSYAN
Underground Mechanical 7/14/2025 Partial Approval KEVIN SARGSYAN
Gas Test 8/12/2025 Corrections Issued HERBERT GIRON
Underground Mechanical 8/12/2025 Partial Approval HERBERT GIRON
Gas Test 8/21/2025 Partial Approval MEL KHACHATOURIAN
Verify Rec and Parks Fee Memo 11/7/2025 Approved KEVIN SARGSYAN
PLUMBING-Final 11/21/2025 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 12/1/2025 Corrections Issued HERBERT GIRON
HVAC-Final 12/1/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 12/1/2025 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 12/11/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 12/11/2025 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 12/11/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/15/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 12/15/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Final 1/7/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/13/2026 Approved KEVIN SARGSYAN
Final 1/13/2026 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 1/13/2026 Approved KEVIN SARGSYAN
Green Building Final 1/13/2026 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 1/13/2026 Not Required KEVIN SARGSYAN
Smoke Detectors 1/13/2026 Approved KEVIN SARGSYAN
Final 5/4/2026 OK to Issue CofO KEVIN SARGSYAN