6116 N MAURY AVE 91367

Certificate Information: 6116 N MAURY AVE 91367

Application / Permit
22010-30000-05821
Plan Check / Job No.
B22WL04378
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
new one story attached ADU 1,196 sf per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 10/17/2023
Issuing Office
West Los Angeles
Current Status
Issued on 10/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/30/2022 APPLICANT
Assigned to Plan Check Engineer 12/28/2022 YASHAR EMAMI
Corrections Issued 1/11/2023 YASHAR EMAMI
Quality Review Completed 1/17/2023 CHIHARU SUZUKI
Applicant returned to address corrections 9/27/2023 YASHAR EMAMI
Plan Check Approved 10/11/2023 YASHAR EMAMI
Issued 10/17/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/8/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 3/8/2023 FERNANDO GIL
Sewer availability Cleared 3/9/2023 FERNANDO GIL
Low Impact Development Cleared 7/6/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/12/2023 FERNANDO GIL
GPI Written Notices Cleared 10/11/2023 YASHAR EMAMI
Grading Pre-Inspection Cleared 10/11/2023 YASHAR EMAMI

Contact Information

Architect Khoudikian,, Kaaren G; Lic. No.: C13183 6906 FOOTHILL BLVD.      TUJUNGA, CA 91042
Contractor Owner-Builder       ,
Engineer Barajas,, Jorge; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/5/2024 Approved GEVORK IPCHYAN
Footing/Foundation/Slab 11/15/2024 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 11/20/2024 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Partial Approval GEVORK IPCHYAN
Wood Frame 3/25/2025 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 6/13/2025 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 6/13/2025 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 7/9/2025 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 7/9/2025 Not Ready for Inspection GEVORK IPCHYAN
Green Building Rough 7/9/2025 Approved GEVORK IPCHYAN
HVAC-Rough 7/9/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 7/9/2025 Not Ready for Inspection GEVORK IPCHYAN
Sewer 7/9/2025 Approved GEVORK IPCHYAN
Wood Frame 7/9/2025 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 8/7/2025 Not Ready for Inspection TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Not Ready for Inspection TROY SANDERS
Grading Pre-Inspection 8/7/2025 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 9/4/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 9/4/2025 Approved GEVORK IPCHYAN
Green Building Rough 9/4/2025 Approved GEVORK IPCHYAN
HVAC-Rough 9/4/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 9/4/2025 Approved GEVORK IPCHYAN
Drywall Nailing 9/22/2025 Partial Approval JON MCHUGH
ELECTRICAL-Rough 11/19/2025 Corrections Issued GEVORK IPCHYAN
Drywall Nailing 5/6/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Final 5/6/2026 Not Ready for Inspection GEVORK IPCHYAN
Final 5/6/2026 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2026 Approved GEVORK IPCHYAN
Green Building Final 5/6/2026 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Final 5/6/2026 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Final 5/6/2026 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Not Ready GEVORK IPCHYAN
Sewer 5/6/2026 Not Ready for Inspection GEVORK IPCHYAN
Smoke Detectors 5/6/2026 Not Ready for Inspection GEVORK IPCHYAN
Drywall Nailing 5/22/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Final 5/22/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 5/22/2026 Approved GEVORK IPCHYAN
Final 5/22/2026 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 5/22/2026 Approved GEVORK IPCHYAN
HVAC-Final 5/22/2026 Approved GEVORK IPCHYAN
HVAC-Rough 5/22/2026 Approved GEVORK IPCHYAN
PLUMBING-Final 5/22/2026 Approved GEVORK IPCHYAN
PLUMBING-Rough 5/22/2026 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved GEVORK IPCHYAN
Sewer 5/22/2026 Approved GEVORK IPCHYAN
Smoke Detectors 5/22/2026 Approved GEVORK IPCHYAN
Final 6/4/2026 Corrections Issued GEVORK IPCHYAN