341 S ANITA AVE 90049
Certificate Information: 341 S ANITA AVE 90049
- Application / Permit
- 22010-30000-05813
- Plan Check / Job No.
- B22WL04371
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 6/12/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | HOOMAN HAJIZADEH |
| Corrections Issued | 12/15/2022 | HOOMAN HAJIZADEH |
| Quality Review Completed | 12/20/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 1/17/2023 | APPLICANT |
| Applicant returned to address corrections | 3/24/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 4/17/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 5/1/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 5/19/2023 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 6/5/2023 | SERGIO SILVA |
| Plan Check Approved | 6/7/2023 | SERGIO SILVA |
| Issued | 6/12/2023 | APPLICANT |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
| CofO Issued | 3/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2023 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/24/2023 | JENSON LEE |
| Specific Plan | Cleared | 2/24/2023 | EDUARDO HERMOSO |
| Hydrant and Access approval | Cleared | 3/13/2023 | KURT CORRAL |
| GPI Written Notices | Cleared | 3/24/2023 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 3/24/2023 | HOOMAN HAJIZADEH |
| Low Impact Development | Cleared | 4/20/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/24/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Blue Label Construction Inc; Lic. No.: 972011-B | 2632 WILSHIRE BLVD #363 SANTA MONICA, CA 90403 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
| Engineer | Rogers,, Jerome Alan; Lic. No.: L5336 | 135 N SAN GABRIEL AVE 100 SAN GABRIEL, CA 91775 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Landscape Architect | , ; Lic. No.: LA2898 | , |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 7/5/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Piling/Pier/Caisson | 7/6/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 7/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/14/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 9/1/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 9/5/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/5/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 9/25/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/27/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Shotcrete | 9/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 10/20/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 10/26/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/27/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | No Access for Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/29/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 11/30/2023 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Steel/Welding | 11/30/2023 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 12/1/2023 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Steel/Welding | 12/5/2023 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/7/2023 | Approved | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 12/8/2023 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 2/12/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/15/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 3/18/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 3/26/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 3/26/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 3/27/2024 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 3/27/2024 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 4/12/2024 | Conditional Approval | KEVIN SARGSYAN |
| Insulation | 4/15/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/22/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/3/2024 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/17/2024 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 5/17/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/23/2024 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/20/2024 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 8/5/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/5/2024 | Approved | STEPHANIE SWANSON |
| Sewer | 8/5/2024 | Approved | STEPHANIE SWANSON |
| Gas Test | 12/10/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 2/5/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/6/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 2/7/2025 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Final | 2/10/2025 | Approved | CARLOS MATAMOROS |
| Final | 3/6/2025 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Final | 3/6/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 3/6/2025 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 3/6/2025 | Approved | JESUS RODRIGUEZ |
| Structural Steel Frame | 3/6/2025 | Approved | JESUS RODRIGUEZ |