4176 E WILLIMET AVE 90039

Certificate Information: 4176 E WILLIMET AVE 90039

Application / Permit
22010-30000-05786
Plan Check / Job No.
B22WL04355
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story SFD w./ att. 1-car garage at middle of the lot
Permit Issued
Issued on 7/5/2023
Issuing Office
Current Status
CofO Issued on 2/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 REZA HAGHIGHAT
Corrections Issued 12/11/2022 REZA HAGHIGHAT
Quality Review Completed 12/12/2022 CHIHARU SUZUKI
Building Plans Picked Up 12/14/2022 APPLICANT
Plan Check Approved 2/17/2023 REZA HAGHIGHAT
Issued 7/5/2023 APPLICANT
CofO in Progress 2/7/2025 THOMAS LOGRASSO
Permit Finaled 2/11/2025 DEROLD HAUFF
CofO Issued 2/11/2025 DEROLD HAUFF
Permit Finaled 2/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/27/2022 AMAAN MALIK
Highway dedication Cleared 12/27/2022 AMAAN MALIK
Miscellaneous Cleared 12/28/2022 DANIEL CORONADO
Frnt yard landscape/Water mgmt Cleared 12/30/2022 DANIEL CORONADO
ZI Cleared 12/30/2022 DANIEL CORONADO
Low Impact Development Cleared 1/12/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 1/17/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 2/2/2023 AMAAN MALIK
Sewer availability Cleared 2/2/2023 AMAAN MALIK
Hydrant and Access approval Cleared 2/8/2023 MATTHEW CRAIG
SB8 RUD Cleared 7/3/2023 LOUIE MILLER

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/31/2023 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 7/31/2023 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/10/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/10/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Reinf. Concrete 8/29/2023 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/29/2023 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/29/2023 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 8/30/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/19/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 7/19/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/23/2024 Approved BRENDAN MORELLI
ELECTRICAL-Rough 7/23/2024 Approved BRENDAN MORELLI
Green Building Rough 7/23/2024 Approved BRENDAN MORELLI
HVAC-Rough 7/23/2024 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 7/23/2024 Approved BRENDAN MORELLI
Insulation 7/30/2024 Corrections Issued THOMAS LOGRASSO
Insulation 8/12/2024 Approved THOMAS LOGRASSO
Drywall Nailing 8/20/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 8/20/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 9/12/2024 Approved THOMAS LOGRASSO
Shower Pan 9/12/2024 Approved THOMAS LOGRASSO
Sewer 10/22/2024 Approved THOMAS LOGRASSO
Underground Mechanical 10/22/2024 Partial Approval THOMAS LOGRASSO
Underground Mechanical 10/31/2024 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 2/4/2025 Approved THOMAS LOGRASSO
HVAC-Final 2/4/2025 Approved THOMAS LOGRASSO
Final 2/6/2025 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 2/6/2025 Approved THOMAS LOGRASSO
PLUMBING-Final 2/6/2025 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Required THOMAS LOGRASSO
Service/Power Release 2/6/2025 Approved THOMAS LOGRASSO
Smoke Detectors 2/6/2025 Approved THOMAS LOGRASSO